U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Murray Road PGE Substation Fire

All POL/SITREP's for this site Murray Road PGE Substation Fire
Beaverton, OR - EPA Region X
POLREP #1
Initial and Final
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Murray Road PGE Substation Fire - Removal Polrep
Initial and Final Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region X

Subject: POLREP #1
Initial and Final
Murray Road PGE Substation Fire
10HQ
Beaverton, OR
Latitude: 45.4343340 Longitude: -122.8295030


To:
From: Daniel Heister, On-Scene Coordinator
Date: 9/16/2009
Reporting Period: 5/17/2009 - 5/18/2009

1. Introduction
  1.1 Background
   
Site Number: NA    Contract Number: NA
D.O. Number: NA    Action Memo Date: 5/18/2009
Response Authority: CERCLA    Response Type: PRP Oversight
Response Lead: EPA    Incident Category: Removal Action
NPL Status: Non NPL    Operable Unit: USEPA, R10, ECL, ERU
Mobilization Date: 5/18/2009    Start Date: 5/18/2009
Demob Date: 5/18/2009    Completion Date: 5/18/2009
CERCLIS ID: NA    RCRIS ID: NA
ERNS No.: NA    State Notification: Yes
FPN#: NA    Reimbursable Account #: NA


1.1.1 Incident Category
Emergency Response

1.1.2 Site Description
Large Residential/Commercial Utility Distribution Substation

1.1.2.1 Location
Beaverton, Oregon

1.1.2.2 Description of Threat
Possible release of PCB's and or oil reaching surface water

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

OSC Heister had seen news coverage of the spectacular blaze on 5/17/2009, the aerial shot showed that the fire was in the midst of residential neighborhoods and commercial businesses.  Heister contacted Andy Smith the Phone Duty Officer in Seattle.  They discussed the situation and agreed that since Heister lived 18 miles from the site it would be worthwhile to contact PGE and make arrangements to meet at the site the following morning.

Heister met Mr. Chip Bloomer, Environmental Services, Portland General Electric (PGE) at the substation approximately ten hours after the transformer fire had been suppressed.  Heister had contacted PGE the afternoon of 05/17/2009 to arrange the meeting and assess the impact of the transformer fire and countermeasures PGE had taken.

Heister met Mr. Bloomer at the site at 0645 hrs on 5/18/2009.  Mr. Bloomer said the large skid mount portable transformer had been brought in to temporarily replace the permanent transformers so that they could be serviced.  Some time on 05/17/2009 the temporary transformer experienced a catastrophic failure and caught fire.  Local fire authorities allowed the fire to burn out which took several hours. Mr. Bloomer and Heister discussed the electrical equipment involved in the fire.  Mr. Bloomer produced sample results for all three peices of equipment.  Two 9 gallon station transformers burned on the skid trailer and they both were non-detect for PCB.  The larger 3120 gallon transformer had dielectric containing 4 ppm PCB.  this is considered to be a non-PCB transformer under TSCA.  I asked Mr. Bloomer if the PCB capacitors located in the far NE corner of the station were impacted and he said no.  They inspected the capacitors and they were in fact intact and unaffected.

Heister then ask Mr. Bloomer to show him the area impacted by the dielectric oil.  This area was slightly down slope from the burn area and covered approximately 800 sq. feet of packed gravel contained on the PGE sub-station property.  Heister asked Mr. Bloomer if any surface water was impacted and he said there was a season creek (Teal Creek) about 400 feet NE of the fire.  He confirmed that it was not impacted.

Heister asked Mr. Blomer what PGE's next steps were.  He said that equipment was stationed outside the sub-station ready to excavate the oil contaminated gravel.  They were waiting for the metal trailer and carcass of the burned transformer to cool so that work could be conducted safely.  Heister verified where the equipment was and in fact there were clean up crews prepared to clean up the site.  Mr. Bloomer told me it was a top priority to get the contamination cleaned up and get the substation operational as soon as possible.

As a former PCB inspector Heister had worked with PGE many times before and was confident a thorough clean up would be conducted.  Heister told Mr. Bloomer to call me if the situation changed dramatically.  Heister left the site at approximately 815 hrs.

 

 

2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative
See Background above

2.1.2 Response Actions to Date
Action was completed 05/21/2009

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
No enforcement action Taken

2.1.4 Progress Metrics

The material was not considered hazardous and went to a sub D landfill.

Waste Stream Medium Quantity Manifest # Treatment Disposal
           
           
           



  2.2 Planning Section
   

2.2.1 Anticipated Activities
None

2.2.1.1 Planned Response Activities
Completed

2.2.1.2 Next Steps
Completed

2.2.2 Issues
None


  2.3 Logistics Section
    No information available at this time.

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    2.5.1 Safety Officer
No safety issues.

2.6 Liaison Officer


2.7 Information Officer


2.7.1 Public Information Officer
None

2.7.2 Community Involvement Coordinator
None

3. Participating Entities
  3.1 Unified Command
After the fire was suppressed there was no Unified Command and the clean up went forward without incident.

3.2 Cooperating Agencies
Tualitin Valley Fire and Rescue, Portland General Electric, and USEPA.

4. Personnel On Site
  See above

5. Definition of Terms
  No information available at this time.

6. Additional sources of information
  6.1 Internet location of additional information/report


6.2 Reporting Schedule
None

7. Situational Reference Materials
  none


Click here to view Attached Images