2.2.1 Anticipated Activities
- Removal and Consolidation With Capping and/or Containment
Prior to excavation of contaminated material, the removal action areas would be cleared and grubbed using a bulldozer or other suitable equipment. Contaminated soil/sediment above cleanup levels will be removed in lifts until confirmation sampling shows cleanup goals have been achieved or a depth of six fee is reached. Contaminated soil deeper than 6 feet is not expected to be removed because it does not currently pose an unacceptable risk to ecological receptors or humans. However, if contamination is visually apparent and accessible below 6 feet, additional material may be removed.
It is anticipated that all or most of the excavated material will be consolidated and placed within the middle reach of the existing creek channel (repository area) prior to capping. Soil/sediment which cannot be placed within the middle reach of the existing channel and capped will be consolidated and contained on the Oeser repository. None of the material known or suspected to be found in the LSCA area exceeds levels that would require treatment before or rather than capping or containment.
The existing creek will be rerouted from the upper portion of the existing creek to the lower historical creek channel. Approximately 700 linear feet of the existing upper creek will be permanently impacted while implementing the removal action. However, approximately 1,300 linear feet of new and historical channel will be constructed, which will have greater functions and values than the existing channel. The creek will not be rerouted through the City’s proposed estuary area in the southern portion of the LSCA.
- Bellingham Technical College (BTC) Outfall Rerouting
The BTC Outfall pipe will be shortened so that it no longer enters the creek near the Birchwood/Oeser Outfall, but instead would enter the creek just south of the existing BTC trail.
- Restoration of the Removal Action Areas
The excavated areas will be backfilled with clean material. It is anticipated that the backfill material may come from clean soil excavated as part of the construction project to create a new parking lot at the adjacent Bellingham Technical College, or from material used to create the new upper creek channel. Impacted wetlands will be restored or mitigated. A wetland delineation will be performed prior to construction, and the details of wetland restoration/mitigation will be determined during the engineering design process.
The middle and upper reaches of the existing creek channel will be capped using clean material excavated to create the new creek channel and/or from the estuary area.
To better delineate the extent of contamination in the excavation areas, pre-removal soil sampling will be performed. Post-removal confirmatory sampling for COCs will also be performed.
2.2.1.1 Planned Response Activities
- Removal and Consolidation With Capping and/or Containment
- Creek Rerouting
- Bellingham Technical College (BTC) Outfall Rerouting
- Restoration of the Removal Action Areas
- Capping
- Sampling
2.2.1.2 Next Steps
Receive sampling results and begin excavating.
2.2.2 Issues
N/A
|