U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

BP Terminal Indianapolis

All POL/SITREP's for this site BP Terminal Indianapolis
Indianapolis, IN - EPA Region V
POLREP #6
Progress PolRep
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
BP Terminal Indianapolis - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #6
Progress PolRep
BP Terminal Indianapolis

Indianapolis, IN
Latitude: 39.8027163 Longitude: -86.2160273


To:
From: Shelly Lam, On-Scene Coordinator
Date: 3/19/2012
Reporting Period: February 16 - March 15, 2012

1. Introduction
  1.1 Background
   
Site Number: Z5K6    Contract Number:  
D.O. Number:      Action Memo Date:  
Response Authority: OPA    Response Type: PRP Oversight
Response Lead: PRP    Incident Category: Removal Action
NPL Status: Non NPL    Operable Unit:
Mobilization Date:      Start Date: 11/14/2011
Demob Date:      Completion Date:  
CERCLIS ID:    RCRIS ID:
ERNS No.:    State Notification:
FPN#: E11504    Reimbursable Account #:


1.1.1 Incident Category
Manufacturing/processing/maintenance - oil and gas storage

1.1.2 Site Description
The BP Indianapolis Terminal (the Site) has operated as a petroleum storage and distribution facility since 1941.  The Site consists of an administrative building, service garage, petroleum distribution rack, miscellaneous warehouse and pumping station sheds, oil/water separator, underground storage tanks (UST) and aboveground storage tanks (AST), which contain gasoline, diesel, ethanol, furnace oil, and heating oil. AST capacity ranges from 672,000 to 3,360,000 gallons, with a total capacity exceeding 18,000,000 gallons.

1.1.2.1 Location
The Site is a 41-acre bulk terminal located at 2500 North Tibbs Avenue in Indianapolis, Marion County, Indiana, 46222.  Site coordinates are 39.8027163 latitude and 86.2160273 longitude.  The Site is bordered by commercial property to the north; shopping plaza to the northeast; Ferguson Industrial Plastics Division and a fire station to the east; undeveloped property to the south; and Little Eagle Creek to the west.

1.1.2.2 Description of Threat
Environmental investigations conducted by BP and its consultants documented that there are  petroleum-related groundwater impacts from benzene, toluene, ethylbenzene, xylenes (BTEX), methyl tertiary butyl ether (MTBE), naphthalene, ethanol, and polynuclear aromatic hydrocarbons (PAH) including benzo(a)anthracene, benzo(a)pyrene, benzo(k)fluoranthene, chrysene, dibenz(a,h)anthracene, and indeno(1,2,3-cd)pyrene beneath the Site.  Light Non-Aqueous Phase Liquid (LNAPL) has been found in a shallow aquifer beneath the Site and at seeps along Little Eagle Creek.  

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
BP has been conducting sampling, monitoring, and cleanup at the Site since 1988.  Data collected by BP shows that BTEX, MTBE, and PAHs have been found across the Site and in Little Eagle Creek as free and dissolved-phase product. 

BP’s Semi-Annual Groundwater Report for the facility dated  July 2010 documented that LNAPL continued to be detected in certain on-Site wells and dissolved phase compounds were as high as 23,900 micrograms per liter (ug/L) for benzene in monitoring well DHW-69; 58,200 ug/L for toluene in monitoring well DHW-72; 2,410 ug/L for ethylbenzene in DHW-55; 9,720 ug/L for xylenes in DHW-72; 262 ug/L for MTBE in DHW-54; and 1,150 ug/L for naphthalene in DHW-55.  As of February 24, 2010, monitoring well DHW-96, adjacent to Little Eagle Creek, had a benzene concentration of 4,250 ug/L.

2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative
The Site was previously in the Voluntary Remediation Program (VRP) of the Indiana Department of Environmental Management (IDEM).  IDEM referred the Site to the U.S. Environmental Protection Agency (EPA) on December 13, 2010.  On November 14, 2011, EPA executed an Administrative Order by Consent (AOC) under Section 311 of the Clean Water Act.  The AOC requires BP to implement removal measures to prevent migration of petroleum hydrocarbon impacted groundwater into Little Eagle Creek.

2.1.2 Response Actions to Date
BP conducted the following activities during the reporting period: 

  • Continued pump and treat system fine tuning; Upgraded system logic controller and antenna;
  • Collected monthly system samples;
  • Conducted semi-monthly operation and maintenance (O&M) of LNAPL recovery system, installed at DHW-110;
  • On February 22, 2012, re-installed compressor at DHW-110 after compressor pump re-build. Compressor was operating normally when field staff departed the site; On February 28, 2012, discovered compressor was having problems building pressure. Compressor was removed and transported to local mechanic for repairs. Air condensate appears to have caused seal failure on air chamber.  Stantec will assess options for an auto-drain to release air condensate build-up in pump chamber to prolong seal life.
  • On March 14, 2012, conducted manual LNAPL recovery on DHW-110 to mitigate recovery downtime while compressor is repaired. Two gallons of LNAPL were recovered;
  • Conducted semi-monthly manual LNAPL recovery and related breathing zone monitoring;
  • Conducted monthly surface water sampling at Little Eagle Creek per the Revised Surface Water and Groundwater Sampling Plan dated February 21, 2012; and
  • Conducted quarterly groundwater monitoring per the Revised Surface Water and Groundwater Sampling Plan dated February 21, 2012.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
EPA executed Docket No. V-W-11 C-984, an AOC with BP on November 14, 2011.

2.1.4 Progress Metrics
Below is a schedule of items included in the AOC:

 

Milestone Date Due Date Done
Effective Date (ED) 11/14/2011 11/14/2011
LNAPL Recovery, Quarterly Creek & MW Sampling 11/14/2011 11/14/2011
Contractor Notification 11/21/2011 11/21/2011
Project Coordinator Notification 11/21/2011 11/21/2011
HASP Submittal 12/6/2011 12/6/2011
QAPP Submittal 12/6/2011 12/6/2011
HASP/QAPP Approval (HQA)   1/5/2012
HASP/QAPP Revisions 1/13/2012 1/13/2012
LNAPL Recovery, Creek Sampling Locations Notification, Quarterly MW Sampling 1/27/2012 1/27/2012
Creek and Groundwater Sampling Locations Revisions 2/17/2012 2/21/2012
Creek Sampling Location Approval (CS)   2/21/2012
Monthly Creek Sampling 3/6/2012 3/6/2012
On-Site Construction 12/14/2011 8/30/2011
Construction Complete 3/19/2012 3/19/2012
Investigation Work Plan 2/12/2012 2/12/2012
Investigation Complete (IC)    
Investigation Report    
Investigation Report Approval (IRA)    
Removal Work Plan    
Removal Work Plan Approval (RWA)    
Removal    
Final Report, 60 days after removal is complete    


  2.2 Planning Section
    2.2.1 Anticipated Activities
The following sections discuss planned response activities and next steps.

2.2.1.1 Planned Response Activities
During the next reporting period, BP will:

  • Continue to provide oversight and documentation support to EPA's On-Scene Coordinator (OSC);

  • Continue post-incident monitoring and analytical results reporting to OSC;

  • Conduct Little Eagle Creek monthly surface water sampling;

  • Continue to optimize pump and treat system in anticipation of re-start; and 

  • Repair of damaged carbon vessels.

2.2.1.2 Next Steps
BP will continue collecting surface water and groundwater samples until the treatment system is operational again.

2.2.2 Issues
The root cause analysis (RCA) investigation associated with the February 4, 2012 release of untreated groundwater was conducted February 14-15 on-site.  The RCA results were provided to EPA in the Post Incident 10-Day Report, submitted February 17, 2012.  The RCA also generated a list of action items to be completed prior to re-starting the system. As such, on February 17, 2012, BP provided EPA a revised schedule and system start-up deadline of March 19, 2012, in order to complete the RCA action items. Bill Wagner of EPA confirmed via email dated March 5, 2012 that the revised schedule was acceptable.

Due to specific monitoring well conditions (bent casing, 1-inch diameter casing), sampling equipment approved in the Quality Assurance Project Plan (QAPP) (submersible pump) could not be used at approximately 6 wells. Stantec communicated this to the EPA OSC on March 9, 2012, and the OSC concluded that sampling via peristaltic pump was approved for wells with either of those conditions for this sampling event.  Sampling methodology in these cases will be noted on field sampling forms as an approved deviation from the QAPP.

  2.3 Logistics Section
    Not applicable (NA)

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    2.5.1 Safety Officer
EPA has approved BP's Health and Safety Plan (HASP).  BP will conduct all environmental work at the Site under the HASP.

2.6 Liaison Officer
NA

2.7 Information Officer
NA

2.7.1 Public Information Officer
NA

2.7.2 Community Involvement Coordinator
NA

3. Participating Entities
  3.1 Unified Command
NA

3.2 Cooperating Agencies
IDEM
Marion County Public Health Department

4. Personnel On Site
  One Superfund Technical Assessment and Response Team (START) contractor was on-Site during creek and groundwater sampling March 6-7, 2012.

5. Definition of Terms
 
AOC Administrative Order by Consent
AST Aboveground Storage Tank
BTEX Benzene, toluene, ethylbenzene, xylenes
ED Effective Date
EPA Environmental Protection Agency
FPN Federal Project Number
HASP Health and Safety Plan
IDEM Indiana Department of Environmental Management
LNAPL Light Non-Aqueous Phase Liquid
MTBE Methyl teriary butyl ether
NA Not Applicable
O&M Operation and Maintenance
OSC On-Scene Coordinator
PAH Polynuclear aromatic hydrocarbons
PolRep Pollution Report
PRP Potentially Responsible Party
QAPP Quality Assurance Project Plan
RCA Root-Cause Analysis
START Superfund Technical Assessment and Response Team
ug/L micrograms per liter
UST Underground Storage Tank
VRP Voluntary Remediation Program


6. Additional sources of information
  6.1 Internet location of additional information/report
Additional information can be found at www.epaosc.org/bpterminalindy.

6.2 Reporting Schedule
The OSC will submit the next Pollution Report (PolRep) on or about April 15, 2012.

7. Situational Reference Materials
  NA