2.1.1 Narrative
At approximately 0720, the Lockport Fire Department responded to the incident. At approximately 0745, the pipeline was shutdown. At approximately 0820, the Responsible Party (RP), West Shore Pipeline (owner) and Buckeye (operator), responded to the incident. In addition, U.S. EPA and its Superfund Technical Assessment and Response Team (START) contractor arrived on-site to conduct oversight of cleanup activities. At this time a Unified Command was implemented with U.S. EPA, Illinois Environmental Protection Agency (IEPA), Lockport Fire Department, and Buckeye. Starting on 12/15/2010, Unified Command consists of U.S. EPA, IEPA, and Buckeye.
Initial air monitoring conducted by West Shore personnel indicated a maximum benzene reading of 6.0 parts per million (ppm) in ambient air. Based on initial air monitoring readings, West Shore personnel delineated the area with high readings as the hot zone. START personnel oversaw West Shore personnel and contractors air monitoring activities. START also conducted air monitoring at spill site and work zones to confirm West Shore air monitoring results. Air monitoring was conducted for oxygen (O2), the lower explosive limit (LEL), volatile organic compounds (VOCs), carbon monoxide (CO), and hydrogen sulfide (H2S).
Center for Toxicology and Environmental Health (CTEH) was contracted by CN Railroad to facilitate the opening of the west track to commuters. CTEH conducted monitoring in the commuter trains as they passed the spill site to ensure commuter safety.
West Shore and Buckeye Pipeline contracted CTEH to conduct air monitoring at the site and in the nearby residential areas. CTEH has utilized AreaRAEs for continuous air monitoring in work zones and residential areas. One AreaRAE is deployed on a moving vehicle that makes rounds in the work zones and residential areas. CTEH collects air samples using summa canisters. Summa canisters are sent for laboratory analysis for VOCs and semi-volatile organic compounds (SVOCs). CTEH personnel have reported that no VOC readings have exceeded background levels in the residential area. VOC readings near the spill have been detected at up to 25 ppm. Respiratory protection is required of on-site workers in the spill area. START personnel are overseeing CTEH air monitoring work as well as conducting and collecting separate air monitoring data points utilized the Rapid Assessment Tool (RAT) system.
West Shore and Buckeye Pipeline cleanup contractors, Future Environmental and Veolia Environmental, are using vacuum trucks to remove the crude oil from the drainage ditch and wetland area. The crude oil is transferred from the vacuum trucks to tanker trucks for off-site transport and disposal. In addition, cleanup contractors are excavating contaminated soil and transporting off-site for disposal.
In accordance with Section 7 of the Endangered Species Act and the rule at 50 CFR Part 402.05, US EPA requested emergency consultation by US Fish and Wildlife Service at West Shore Crude Line S0257EM in Lockport, Illinois. US Fish and Wildlife Service is on-scene and providing input on response actions.
2.1.2 Response Actions to Date
West Shore contractor, Midwest Mechanical, has placed a temporary clamp on the pipeline break. The break is at the bottom of the pipe and is approximately the size of a quarter. The pipeline is approximately six feet below ground. Buckeye submitted a plan to Department of Transportation (DOT) Pipelines and Hazardous Materials Safety Administration (PHSMA) to conduct an integrity test. The plan was accepted and the test was conducted on the pipeline by Midwest Mechanical. The pipeline passed the integrity test on 12/16/2010.
East of the railroad tracks, in the drainage ditch, excavation of contaminated soil has commenced. Soil excavation started from the furthest north and the furthest south extents working toward each other. Vac trucks are continuing to collect free product in the drainage ditch.
West of the railroad tracks, vac trucks are collecting free product in the wetland areas adjacent to the access road. START conducted product and soil sampling activities near the culvert connecting the drainage ditch to the wetlands.
As of 12/17/2010 at approximately 0900, an estimated 20,000 gallons of crude oil had been recovered from the drainage ditch and wetland area. In addition, approximately 650 cubic yards (yd3) of contaminated soil has been removed from the drainage ditch. Recovery operations on 12/14/2010 and 12/15/2010 were slow due to the low temperatures freezing valves on vac trucks and frac tanks and the viscosity of the product.
Discussions were held to determine preliminary remediation options of the impacted wetlands area between Buckeye, U.S. EPA, IEPA, DOT, USFWS, IDNR, and a representative of the wetlands property owner.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
The RPs, West Shore Pipeline and Buckeye Pipeline, have responded to the incident and have contractors working to recover the crude oil.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|