Site Number: |
B4F1 |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
|
Response Authority: |
CERCLA |
|
Response Type: |
PRP Oversight |
Response Lead: |
PRP |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
1/31/2011 |
|
Start Date: |
1/31/2011 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
|
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
1/31/2011 |
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Site Description
Welch Group Environmental (WGE) operated a business that recovered lead and other metals (i.e copper) from spent munitions at firing ranges gathered from around the Southeast. They then melted the lead into ingots.
The WGE Belton site conducted material separation as well as distribution of recycled material. In addition, several hundred drums of 'salt formations' are present in drums which are in various conditions.
The WGE Fair Play site conducted material separation as well as melting activities and also has up to 50 drums of uncontained process material and liquids.
Both site operations were conducted without South Carolina Department of Health and Environmental Control (SCDHEC) permits. SCDHEC documents that up to 10 WGE employees had significantly high lead levels. SCDHEC ordered the cessation of operations on 12-02-2010. SCDHEC referred the sites to EPA R4 Emergency Response and Removal Branch (ERRB) for removal site evaluation (RSE) on 12-22-2010.
The EPA On Scene Coordinator (OSC) began the removal site inspection during the week of 01-31-2011. In coordination with Air, Waste and Land Management, Site Evaluation, and Region 1 programs at SCDHEC, the OSC has directed the potentially responsible parties (PRPs) to secure the locations, contain and secure open vessels/drums and construct a sediment/soil containment measure such as silt curtain and hay bales where appropriate.
The PRPs have hired a qualified contractor. Both Health and Safety as well as Removal Action Workplans (RAWPs) have been submitted and approved by the OSC in consult with SCDHEC. Emergency work commenced on 02-08-2011.
The OSC will continue to coordinate enforcement activities with SCDHEC. In addition, the OSC is coordinating with EPA R4 RCRA to assure that WGE proposed gun range recovery activities meet with applicable federal Resource Conservation and Recovery Act (RCRA) standards.
-
1.1.2.1 Location
Fair Play, SC
1.1.2.2 Description of Threat
Lead is present at high levels in either soils, sediments, uncontained vessels/drums, lead melting process shed, several onsite dump sites, various equipment and brick supplies. These high levels exist at concentrations that are an imminent and substantial threat to public health or welfare.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
The RSE Report has been completed and submitted to the EPA (RSI Report). See SCDHEC referral package at the documents section of for this site: SC DHEC Referral Letter
|