|
|
2.1.1 Narrative
2.1.2 Response Actions to Date
On 9 June 2012, the EPA
Region 6 PDO contacted the Response Duty OSC and START-3 and informed them of a
potential response to a train derailment that happened on 3 June 2012, and the
Response Duty OSC and START-3 were to leave on the morning of 10 June 2012.
10 June 2012, at
approximately 1230 EPA OSC Mike McAteer and START-3 arrived on site. Upon
arriving, EPA and START-3 collected facts regarding the incident and took photo
documentation of the derailment site. START-3 observed and recorded the rail
car numbers, as well as utilizing a hazcat kit to try and identify the two
unknowns. OSC McAteer and START-3 viewed the affected creek, and a pH
between 11 and 12 was observed at a location close to the creek entry point
downstream of the derailment location. OSC McAteer contacted Union Pacific
representatives in regards to the spill, and informed them that Union Pacific
needed to activate and mobilize clean up contractors to the site immediately.
OSC McAteer also contacted the Denison water department and informed them of
the situation. Union Pacific clean up contractors, United Professional
Services, arrived on site at 1610 and started cleanup activities in Shawnee
Creek. Conestoga-Rovers and Associates, another Union Pacific contractor,
arrived on site to document and map the extent of the release and also to
take samples within the creek and Randell Lake. A vacuum truck also arrived on
scene to start removal of the contaminated water within Shawnee creek. Union
Pacific contractors worked until sundown on vacuuming the creek.
11 June 2012, EPA continued to monitor and document cleanup activities. The RP
began flushing activities along the ditch on Highland Drive, and all flush
water was collected and stored on site in frac tanks. The RP began excavating
soil at the incident location, and all soil that was excavated was stored on
site (UP switching yard) in a poly lined bermed area. A second poly liner was
placed over the contaminated soil and secured in place to prevent precipitation
from infiltrating soil. A diversion trench was created at the drainage ditch
along the railroad easement to prevent water from flowing into Shawnee Creek.
The diversion trench will be pumped out if any water pools within the trench.
RP began removing product from within the derailed hopper cars utilizing an
auger. The product is stored in super sacks and placed in an area where the
owner can collect the soda ash and remove it off site. Two (2) TCEQ
representatives were on site to document activities. Rain and possible
thunderstorms are predicted for tonight. Containment measures are in place. A
rain event occured in the early morning hours of 11 June 2012, producing
appoximately 0.31 inches of rain.
12 June 2012. EPA
continued to monitor and document cleanup activities. START-3 took pH levels of
the ditch along Highland Drive, inside Shawnee Creek, and containment measures
on-site. The highest pH level found in Highland Drive ditch and Shawnee Creek
was around pH 8, and the highest pH level found in containment measures on-site
was around pH 12. Containment trench along drainage ditch on railroad easement
was pumped out utilizing a stationary pump that was put in place the night
before. A staging area was created on the west side of Highland Drive for the
storing of empty hopper cars. Trees and vegetation had to be removed. Soda ash
stored in super sacks were moved further into the UP switching yard, and
covered with plastic and poly liners. First hopper car was emptied of soda ash,
and was transported across Highland Drive to the staging area. Work began on
the second hopper car removing soda ash. One (1) TCEQ representative was on
site to document activities and pH levels. A rain event occured throughout the
overnight hours, and totalled approximately 1.0 inches of precipitation.
13 June 2012. EPA continuned
to monitor and document cleanup activities. START-3 took pH levels of the ditch
along Highland Drive, inside Shawnee Creek, and containment measures on-site. A
pH level of 11 was discovered at an earthen berm in the ditch along Highland
Drive next to a leaking vacuum truck. The water was removed by the vacuum
truck, and CRA, a UP contractor, tested the water inside of the truck for pH
and discovered a level of 11.03. It was later determined the vacuum truck
offloaded a second vacuum truck that was at the derailment site, and did not
offload the water after the transfer. Shawnee Creek had a pH 8, and the highest
level of pH found at derailment site was pH 12, inside containment measures. A
second auger was brought in, for a total of two (2) augers and crews removing
soda ash from derailed hopper cars. A second hopper car was emptied and
transported across Highland Drive to staging area. One (1) TCEQ representative
was on site to document activities and pH levels. A rain event occured in
the early morning, and again in the mid afternoon totalling approximately
.10 inches of precipitation.
14 June 2012. EPA continued to monitor and document cleanup activities. START-3
took pH levels of the ditch along Highland Drive, inside Shawnee Creek, and
containment measures on-site. The third and fourth empty hopper cars
were removed from site and staged at the empty hopper car staging area west of
Highland Drive, car numbers TGSX 443552 and FMLX 51286. Shawnee Creek had a pH
of 8, and the highest level of pH found at derailment site was pH 11,
inside containment measures. Excavation of soil from derailment site is
stored on-site for disposal. Access to fifth rail car was made, and emptying of
fifth rail car will start 15 June 2012. Two (2) TCEQ representatives were on
site to document activities. A thunderstorm came through the area in the early
hours of the morning and dropped no more than .25 inches.
15 June 2012. EPA continued to monitor and document cleanup activities. START-3
took pH levels of the ditch along Hightland Drive, inside Shawnee Creek, and
containment measures on-site. Fifth hopper car, car # FMLX 52066, was emptied
and moved across to empty hopper car staging area, west of Highland Drive.
Excavation of contaminated soil was observed, and all soil removed from
incident location was transported and stored on-site for disposal. Sixth hopper
car, car # FMLX 52020 was moved further up the railroad easement towards
Highland Drive for easier access for auger crews. A seventh hopper car, car #
FMLX 51360, was rolled over in an attempt to empty contents for excavation, and
moved further up the railroad easement towards Highland Drive so auger crews
can remove the rest of the contents. A disposal site was identified
for contaminated water in frac tanks. Water will be transported by
Cheney Trucking to Agricultural Services, Inc. 301 West Louis Street, Hutchins,
TX 75141. Maximum pH levels observed by START-3 in Shawnee Creek was pH 8,
highest pH found at derailment site was pH 11 (inside containment trench). A late
afternoon thunderstorm skirted east of the job site and dropped just a trace
amount of rainfall on the site.
During 16-18 June
2012, EPA continued to monitor and document cleanup activities. START-3 took pH
levels of the ditch along Highland Drive, inside Shawnee Creek, and containment
measures on-site. Hopper car numbers five (FMLX 52066), six (FMLX 52020), seven
(FMLX 51360), eight (TGSX 443526), and nine (FMLX 51106) were emptied and moved
to empty hopper car staging area, west of Highland Drive. Excavation of the
site to remove released soda ash and contaminated soil began, all soil and soda
ash removed from site was staged at a bermed, poly lined area and covered with
visqueen to prevent water infiltration.
During 18-25 June 2012, EPA continued to monitor and
document cleanup activities. RP contractor activities included maintaining
containment measures on site, excavation of derailment site, and CRA conducted
field pH testing of soil to ensure proper area and depth was being achieved.
All soil was staged on-site for removal in a bermed, poly lined area and
covered with visqueen to prevent rain water infiltration. On 20 June 2012, CRA
took soil samples which were analyzed by Pace Analytical Services, Inc. located
at 400 W. Bethany Rd., Suite 190, Allen, Texas, 75013: (972).727.1123. Sample
results indicated a high pH in several locations. RP contractors re-excavated
the area in an attempt to remove contaminated soil. OSC McAteer and START-3
observed empty hopper cars being cut into 18”x18” sections by RP contractor
Progress Rail Services Corporation, utilizing a cutting torch. All metal
sections were transported off site to a scrapping facility in Oklahoma.
On 25 June 2012, EPA continued to monitor and document clearnup activities.
Remediation activities expanded to areas beneath new rail line due to possible
soda ash in the base material. RP contractors utilized an undercutter to remove
soda ash and contaminated soil beneath the new rail line. During undercutting
activities, two (2) areas were noted for having high amounts of soda ash
underneath the track. After undercutting of an area was completed, RP
contractors flushed the track with a pH 4 solution of sulfamic acid and water.
All flush water was collected and staged onsite in frac tanks for removal.
Backfilling of the area beneath the rail line utilizing ballast rock was
completed to re-open the rail line.
During 26 June through 5
July 2012, EPA continued to monitor and document cleanup
activities. RP contractors removed the interceptor trench located along the
eastern edge of the derailment site, and created smaller containment measures
for high pH water seeps observed in the area. RP contractors began backfilling
the derailment site utilizing soil obtained from a local quarry, excavators,
trucks, a bulldozer, and a compactor. Backfilling of the derailment site was
completed on 5 July 2012.
During 6-7 July 2012, EPA continued to monitor and document cleanup activities. RP contractors
constructed a permanent containment measure utilizing excavators, trucks, and a
bulldozer along the derailment site to mitigate possible off site migration of
elevated pH runoff that may occur during a rain event. Containment measure
consists of a trench dug into compacted clay along the incident location
approximately six (6) feet wide and sloping from two and a half (2.5) feet down
to ten (10) feet at the lowest points, and the trench was filled with ballast
rock. At each low point, a sump was installed with automated pumps to remove
elevated pH water from the trench to a staged frac tank on-site. The frac tank
is equipped with a sensor which notifies RP contractors when the frac tank
needs to be emptied. The containment trench extends approximately 140 yards
across the length of the derailment site.
On 10 July 2012, START-3
visited the site to monitor and document cleanup activities. After a
significant rain event, a seep of pH 11 liquid was observed approximately ten
(10) yards east of the containment trench, and a large seep of pH 11 water was
observed approximately fifty (50) yards east of the containment trench. Both
high pH seeps migrated directly into Shawnee Creek. OSC McAteer notified RP via
e-mail stating the EPA considers this to be the second release of a pollutant/contaminant to
the waters of the United States, and RP needs to mitigate discharge of
contaminants to Shawnee Creek. RP contractors constructed containment measures
around both seeps utilizing hand held tools, and used powdered sulfamic acid
and a pH 2 solution of sulfamic acid and water to neutralize the high pH liquid
before discharging to Shawnee Creek. The containment measures were intended to
prevent liquids from entering Shawnee Creek.
During 11-17 July
2012, START-3 continued to make site visits to monitor and document cleanup
activities. RP contractors continued remediation activities and extended the
containment trench east approximately one-hundred (100) yards. The total length
of the containment trench is approximately two-hundred and forty (240) yards.
Surveying of the area was conducted by CRA, and RP contractors used hand held
tools to excavate along the rail line to evaluate if elevated pH liquid
extended past the existing containment measures. No areas were observed to
indicate high pH liquid had migrated further east of the existing containment.
UP contractors began disposing of contaminated soil staged on UP property at
Waste Management’s Hillside Landfill located at 1102 Nelson Road, Sherman,
Grayson County, Texas, 75091. Subsequently EPA released START-3 from the incident.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|