U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
SW Energy Ruby Ranch Road Blowout - Removal Polrep
Final Removal Polrep
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region VIII
|
Subject:
|
POLREP #3
SW Energy Ruby Ranch Road Blowout
Z8FF
Green River, UT
Latitude: 38.8099500 Longitude: -110.0616400
|
To:
|
|
From:
|
Curtis Kimbel, OSC
|
Date:
|
12/8/2014
|
Reporting Period:
|
|
1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
Z8FF |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
|
Response Authority: |
OPA |
|
Response Type: |
Emergency |
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
5/21/2014 |
|
Start Date: |
5/21/2014 |
Demob Date: |
6/6/2014 |
|
Completion Date: |
9/30/2014 |
CERCLIS ID: |
|
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
E14810 |
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Removal action.
1.1.2 Site Description
The site is well pad GOVT SMOOT 3, located in the Salt Wash Field of the Paradox Basin, an arid, desert region of eastern Utah. The well blowout occurred sometime during the evening of May 20 when a plug on the well head piping failed resulting in an uncontrolled release of crude oil and production water at an estimated rate of 100 bbs./hr. (The oil/water ratio was unknown.)
The spill was tracked for about 2.5 miles down a 4.5 mile dry wash that is a tributary to the Green River. OSC Merritt arrived on scene and instructed the responsible party to procure the services of an OSRO contractor and oversaw initial response efforts consisting of the construction of a series of berms and a pair of underflow dams and the strategic placement of boom. OSC Merritt supervised the installation of the first underflow dam and carefully walked through the construction process and location for the second underflow dam.
OSC Merritt and Bart Kettle, Division of Natural Resources (UT DOGM), were satisfied the initial response efforts were adequate to keep the spilled material from reaching the Green River and returned to their respective offices. Unfortunately, the second underflow dam was not completed on Friday, May 23. An unusually extreme rain/hail storm occurred on the night of Friday, May 23, that resulted in an unknown amount of material reaching the Green River. As a result, OSC Kimbel was deployed to the site. On Saturday, May 24, the second underflow dam was completed. Another rainstorm Saturday night moved much of the material again but was contained in the second underflow dam and did not reach the Green River. Had the second underflow dam been completed Friday, May 23, per OSC Merritt’s instructions the material would have been contained in the dry river bed and would not have reached the Green River.
SW Energy consists of five children who inherited several wells from their father when he passed a few years ago. The family has never experienced a spill event and thus had very little knowledge of spill related techniques and methodologies. The family relied heavily on the expertise of the federal and state representatives involved and were extremely cooperative during all phases of the response.
1.1.2.1 Location
The well pad is in a remote area of Utah. The site is 14 miles southeast of Green River, Utah, and 165 miles southeast of Salt Lake City
1.1.2.2 Description of Threat
The spill occurred in a dry wash that flows 4.5 miles to the Green River. According to Don Stephens, Natural Resources Specialist for BLM who walked the area on Sunday, May 25, and Monday, May 26, the dry wash contains no endangered or threatened species. An unknown quantity of spilled material reached the Green River, which was flowing at 8,000-14,000 CFS. Green River has a drinking water intake on the river and the area of the river potentially impacted does contain sensitive habitat and endangered environmentally sensitive areas. This is a critical time period for spawning for the endangered and sensitive sucker species and their larvae. OSC Kimbel, Bart Kettle (UT DOGM) and Rosanne Smoot (RP) visited the only nearby property owner, Curtis Rozman of Ruby Ranch, and were told the ranch imports drinking water for the family from a location 15 miles away and does not use drinking water wells on their property.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
When OSC Steve Merritt arrived on the day after the spill occurred, May 21, two ponds had been built 300 feet from the well to capture the fluids. Crews were pumping out the ponds into holding tanks near the site and additional quantities of fluids were taken to Danish Flats. Equipment arrived at 6 p.m. that evening to kill the well and stop the flow.
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
The well was capped by mid-day on May 22. The owners quickly contacted two contractors; Custom Environmental Services (CES) and KSue, a local construction company. The contractors arrived on site and built a series of berms and a pair of underflow dams (as discussed above). In addition, CES placed boom strategically throughout the dry river bed and at the confluence of the dry river bed and the Green River.
OSC Kimbel arrived the morning of Sunday, May 25. A formal Unified Command was created with representatives from SW Energy, EPA, BLM and UT DOGM and CES that met each morning and evening. The site was broken up into four sections consisting of the well pad and the upper, middle and lower sections of the contaminated riverbed. Strategies were developed for each section, which differed greatly due to rough terrain, ledges and difficult access. Workload was divided among the contractors based on training and capability. Appropriate equipment was identified and ordered, which was complicated by the Memorial Day holiday. Mechanized excavation of contaminated soil began on the accessible areas, though much of the original work in the dry riverbed required hand clean up. Contaminated material was collected in a bermed area lined with plastic. Samples were taken of the contaminated material, and disposal options were identified.
2.1.2 Response Actions to Date
EPA, UT DOGM, BLM, SW Energy and CES walked the entire site each day to review progress, to develop mutually agreeable strategies addressing the remaining material, and to ensure all parties agreed on the level of cleanup required. Walking the site each day allowed Unified Command to create accurate projections of time required to complete the cleanup, costs, equipment and manpower requirements, and to identify potential motorized vehicle access points to the dry river bed that would increase effectiveness and speed up the cleanup process.
As of Wednesday morning, May 28, cleanup was progressing rapidly. OSC Kimbel returned to Denver on May 28 and Bart Kettle of UT DOGM oversaw day-to-day activity on the site. OSC Kimbel returned to the site on Tuesday, June 3, to walk the entire area with Cliff Giffen of BLM, representatives of Unified Command and CES to review status of the cleanup. During the meeting on June 3rd it was determined that the Emergency Response phase was complete, and EPA transfered oversight to BLM and UT DOGM for any additional work required on the well and surrounding area.
OSC Kimbel briefed UTDEQ Water Quality (John Whitehead) and UTDEQ Emergency Response (Dale Urban) on Tuesday, May 27.
On September 22, 2014, Brian Smoot (RP) notified OSC Kimbel that the well had been permanently plugged.
On September 30, 2014, UTDOGM and BLM were confident the spill cleanup had been successfully completed.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
SW Energy is the Responsible Party
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.2 Planning Section
|
|
|
No information available at this time.
|
|
2.3 Logistics Section
|
|
|
No information available at this time.
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
No information available at this time.
|
3. Participating Entities
|
|
3.1 Unified Command
US EPA, Curtis Kimbel (OSC) and Steve Merritt (OSC)
SW Energy (4 members of the Smoot family led by Rosanne Smoot)
BLM (4 individuals from their Moab, Price and Monticello offices)
UT DOGM (Bart Kettle)
3.2 Cooperating Agencies
EPA
BLM
UT DOGM
UTDEQ Water Quality
|
4. Personnel On Site
|
|
In addition to UC above:
Custom Environmental Services (OSRO), 8 personnel
KSue Construction, 2-3 personnel
Various contractors cleaning up equipment at the well head, 6 personnel
|
5. Definition of Terms
|
|
No information available at this time.
|
6. Additional sources of information
|
|
No information available at this time.
|
7. Situational Reference Materials
|
|
No information available at this time.
|
|
|