|
|
Site Number: |
10MZ |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
8/14/2014 |
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
9/8/2014 |
|
Start Date: |
9/8/2014 |
Demob Date: |
11/10/2014 |
|
Completion Date: |
11/10/2014 |
CERCLIS ID: |
WAD980977847 |
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Inactive Production Facility
1.1.2 Site Description
1.1.2.1 Location
The Site is located at 18 Blackbird Drive, Inchelium, Ferry County, Washington, 99138 on the Colville Reservation. The Site is mostly located in Section 12 (with a small portion in the Section 1) of Township 32 North, Range 36 East, Willamette Meridian (latitude 48° 17' 40" north, longitude 118° 12' 23" west).
The area surrounding the Site is a mixture of rural and residential, with several residences located to the north, south, and northwest of the Site.
For additional details, please refer to POLREP 1.
1.1.2.2 Description of Threat
Substantial environmental information exists about the Site. Environmental investigations completed at the Site in the 2000s show that soil and groundwater are contaminated with arsenic, chromium, and copper and that the source of these metals is wood treatment operations using chromated copper arsenate (CCA). CCA-contaminated sludge and wastewater are present in containers at the Site, including above-ground storage tanks (ASTs) and sumps. Spent formulations, residuals, drippage, and other wastewaters from wood preserving processes that use arsenic or chromium (i.e., CCA) are RCRA listed hazardous wastes (waste code F035).
In addition to arsenic, chromium, and copper, lead is also a contaminant of concern (COC) at the Site. Although the source of the lead contamination has not been determined, lead has been detected in Site soil at concentrations as high as over 100 times the natural background levels for Washington State and over 10 times the Site cleanup level. The lead contaminated soil known to be at the Site is mostly collocated with contamination from wood treating chemicals.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
2008 - URS Site Investigation
URS conducted a Site investigation at IWTP in July-August 2008. The field investigation concluded that soil and concrete at IWTP is contaminated with metals, including chromium, copper, arsenic, and lead, at concentrations exceeding established Site-specific cleanup levels, which were based on Washington Department of Ecology Model Toxics Control Act (MTCA) cleanup levels. The URS report estimated that approximately 6,000 cubic yards/tons of soil are contaminated with metals.
2014 – EPA Removal Assessment
In May 2014, the EPA performed a removal assessment at the Site, which involved the collection of soil, concrete, water (surface water, wastewater, and groundwater) samples. The purpose of the sampling event was to further delineate specific areas of the Site (e.g., the UCV and portions of the Treated Wood Storage Area [TWSA}) and to determine whether Site materials were characteristic hazardous wastes.
EPA confirmed elevated levels of metals including arsenic, chromium, and copper in soil and concrete at the North and South Drip Pads and Treated Wood Storage Area and delineated the extent of metals contamination in soil in specific areas of the Treated Wood Storage Area. EPA determined that the metals-contaminated soil at the Site did not fail the TCLP analysis for metals and so is not a RCRA characteristic hazardous waste. However, some of the metals-contaminated concrete is a RCRA characteristic hazardous waste (for chromium), as determined by TCLP metals analyses. EPA also determined that the wastewater present in the Retort Chamber Sump and the UCV is a RCRA characteristic hazardous waste (for arsenic), as determined by a comparison of total metals results to TCLP limits.
For additional detail, please refer to POLREP 1.
|
|
|
2.1.1 Narrative
The Scope of Work for the IWTP removal action includes:
- Removal disposal of contaminated concrete in the North Drip Pad, South Drip Pad, and Treatment Building.
- Excavation and disposal of contaminated soil in the NDP, SDP, TWSA, and the Treatment Building.
- Decontamination and disposal (by recycling) the retort, 9 ASTs, and piping in the Treatment Building and 2 ASTs in the Tank Enclosure.
- Removal and disposal of liquids and sludge found or generated in ASTs, retort, and/or the UCV.
- Removal and disposal of the UCV.
During this reporting period (11/1/2014-11/10/2014), the following removal activities occurred:.
- Treatment Building: Final samples collected from the stem wall of the Retort Chamber Sump passed TCLP indicating that contamination has been successfully removed. ERRS leveled the Treatment Building floor and backfilled. Openings into the TB were boarded up and locks were installed on all doors to restrict access. All work in the TB has been completed.
- Treated Wood Storage Area: The remaining contaminated soil stockpiled in the Central TWSA has been removed and trucked off site. All TWSA areas were backfilled, compacted, and re-graded. All removal work in the Western, Northern, Northeastern, and Central TWSAs have now been completed.
- Off-site Transportation and Disposal: During this reporting period, a total of 129 trucks were loaded with contaminated material and sent off-site for disposal. 120 trucks (3661.41 tons this week/17,047.80 tons to date) of non-hazardous waste soil were sent to an appropriate disposal facility. Nine trucks (285.60 tons this week/1,048.90 tons to date) of hazardous waste concrete were sent to an appropriate disposal facility. All contaminated materials have now been removed from the site and disposed.
- Final Demobilization Tasks: Blackbird Drive and the Western Road were improved and re-graded; road delineators were installed; monitoring well monuments were improved and marked by stakes; equipment was decontaminated and staged for vendor pick up.
- Tank Enclosure ASTs: All work in this operational unit was completed W/E 10/4/2014.
- North Drip Pad: All work in this operational unit was completed W/E 10/11/2014.
- South Drip Pad: All work in this operational unit was completed W/E 10/11/2014.
- Blackbird Drive: All work in this operational unit was completed W/E 10/18/2014.
- Underground Containment Vault: All work in this opoerational unit was completed W/E 11/1/2014.
2.1.2 Response Actions to Date
An Action Memo was prepared and signed by EPA on August 14, 2014.
Five Underground Storage Tanks, located on the east side of the Maintenance and Treatment Buildings, were removed several years ago (date uncertain).
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
A Settlement Agreement between EPA and Colville Tribal Enterprise Corporation (CTEC) was signed on August 22, 2014. The settlement agreement provides funds from CTEC to EPA to conduct this removal action.
2.1.4 Progress Metrics
Below is a summary of material transported off site during this reporting period:
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
F035 Concrete debris |
Concrete |
285.60 tons during this Operational Period; 1,048.90 tons removal total |
multiple |
TBD |
RCRA Subtitle C landfill, Grandview ID |
Non-hazardous waste soil |
Soil |
3,661.41 tons during this Operational Period; 17,047.80 tons total |
multiple |
TBD |
RCRA Subtitle D landfill, Boardman, OR |
F035 Wastewater |
Liquid |
0 gallons during this Operational Period; 9,186 gallons total |
multiple |
TBD |
US Ecology, Grandview, ID |
|