Property #1:
EPA ERRS contractor mobilized to the site on September 8th, along with an excavator, skid steer and front end loader. Demolition began and completed on September 9th. The approved landfill was closed for several days due to the weather, so demolition debris was properly staged on site for later disposal.
Property #2
EPA ERRS contractor mobilized to the second property on September 9th and began demolition activities on September 10th. The ACM was located in the window glazing, and prior to demolition activites, the windows were removed and disposed of at the first property. The approved landfill was closed for several days due to the weather, so demolition debris was properly staged on site for later disposal.