U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Welch Group Environmental (WGE) Palmetto Hwy

Notices

All Notices [1] rss feed
Categories
Notices  Posted Category
Removal Site Inspection Report 3/9/2011 START RSI Report

March 9, 2011

Mr. Leo Francendese

On-Scene Coordinator (OSC)

U.S. Environmental Protection Agency

61 Forsyth Street, SW 11th Floor

Atlanta, Georgia 30303

 

Subject:           Removal Site Inspection, Revision 0

                        Welch Group Environmental (WGE) Palmetto Parkway Site

                        110 Palmetto Parkway, Belton, South Carolina

                        EPA Contract No. EP-W-05-053

                        Technical Direction Document (TDD) No. TNA-05-001-0129

Dear Mr. Francendese:                                                             

The Oneida Total Integrated Enterprises (OTIE) Superfund Technical Assessment and Response Team (START) have prepared this Incident Response Letter Report detailing activities conducted in support of the On Scene Coordinator (OSC) for the U.S. Environmental Protection Agency (EPA).  The initial scope of this activity was to conduct field investigation activities at the Welch Group Environmental (WGE) Palmetto Parkway site (site) in support of a removal site inspection that was part of a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) removal site evaluation (RSE).  The OSC directed WGE to conduct an emergency response action at the site thus expanding START’s support role.  WGE is a metal recovery company that recovered lead slugs and shell casings from gun/rifle ranges until it ceased operations in December 2010 at the request of the South Carolina Department of Health and Environmental Control (SCDHEC).  The site is part of WGE's operations and was serving as storage.  

START was specifically tasked to prepare a Health and Safety Plan; provide equipment including an X-Ray Fluorescence (XRF) instrument, and personnel to conduct inspection and support activities; document START and Responsible Party (RP)-lead response action site activities with photographs and written logbook notes; maintain the OSC webpage (EPAOSC Webpage) and prepare an Incident Response Letter Report summarizing the inspection and emergency response action activities.  Attachment A of this Letter Report includes a topographical map (Figure 1), a site aerial photograph (Figure 2) and XRF screening location maps (Figure 3) and (Figure 4), respectively.  The XRF decontamination test results are presented in Table 1 provided in Attachment B (Pilot Test Data).  A photographic log of site activities is provided as Attachment C (Photolog) and a copy of the logbook notes are provided as Attachment D (EPA Field Notes).

Physical Location 

The site is located at 110 Palmetto Parkway in Belton, Anderson County, South Carolina.  The geographic coordinates for the center of the property are Latitude 34.5228881° North and Longitude -82.4942948° West (Figure 1).  The site is comprised of a one-story warehouse building where WGE stored recovered lead slugs and shell casings from gun/rifle ranges.  Several different clients lease space within the multi-use warehouse, but the building is not partitioned into individual units.  Residential properties are located to the east, west, and south of the warehouse building.  A large one-story warehouse building bounds the site to the north.  (Figure 2) located in Attachment A show the location of the site and the surrounding areas.

Site Background

This site is part of the WGE CERCLA response.  SCDHEC notified EPA of the site while EPA was conducting Removal Site Evaluations (RSE) at two other WGE facilities located in Fair Play (Fair Play Facility) and Belton (Belton Facility Webpage), South Carolina.  The WGE Palmetto Parkway site was part of WGE's operations and served as warehouse storage.  

On February 7, 2011, EPA, START, property owner Cummings Gary, and site operator WGE conducted a site walk.  During the site walk, WGE indicated that a box of range recovered material had overturned during cleanup and a metal shovel was used to recover the spilled material (AccessAgreement).  During recovery, the metal shovel scraped against the residual gun powder (green powder) covered concrete floor creating a spark. The ensuing fire partially damaged the building leaving burnt insulation and roofing material.  

Field Investigation Activities and Results

During the February 7, 2011 site walk, the EPA OSC tasked START to use an XRF to conduct in situ screening for metal concentrations at select locations of the building.  START screened the floor and walls of areas where most site operation activities took place.  WGE operations occupied approximately 4,000 square feet (ft2) of warehouse space.  XRF readings for lead ranged from 408 parts per million (ppm) on the warehouse floor to 35,000 ppm along the building walls.  Figure 3, provided in Attachment A, shows the building layout and the XRF lead readings (Figure 3). 

Based on the XRF lead screening results, the EPA OSC determined that a release or substantial threat of release of a hazardous substance to the environment had occurred.  The release exists at high concentrations at or near the surface that present an imminent and substantial threat to public or welfare (Pol/Sitrep #1). 

On February 10, 2011, a Notice of Federal Interest (NOFI) was issued to the site owner, Mr. Cummings Gary (NOFI).  The OSC directed the site operator, WGE, to remediate the contaminated section of the warehouse.  WGE’s immediate goal was securing the facility from other facility personnel. 

RP-Lead RA Actions

On February 17, 2011, WGE contractor was on site to cover the concrete flooring in designated areas with an industrial paper until remediation activities could occur.  Safety barricades were used to delineate the exclusion zone (area where WGE stored the range recovered material) to prevent non response-related personnel from entering.  WGE contractor submitted a Pilot Test Work Plan proposing decontamination of approximately 1,400 ft2 of the warehouse floor to determine contaminant reduction concentrations below the EPA regional screening levels (RSL) of 400 ppm (Approved Work Plan).  

On February 21 and 22, 2011, Phillips was on site to conduct the decontamination Pilot Test.  Pilot testing was performed in a small area of the warehouse floor near the loading docks.  Initial XRF readings for lead near the loading docks ranged from 1,399 to 1,570 ppm (Figure 3).   The concrete near the loading docks was smooth in some areas and pitted and showing signs of deterioration in others.  A detergent solution and water was used to clean the small area.  The area was then rinsed with minimal water, vacuumed, and allowed to dry before confirmation screening using the XRF.  A steel wire brush was used by WGE contractors in several areas to determine its effectiveness.  Table 1, provided in Attachment B, presents the results of the February 21 and 22, 2011 Pilot Test XRF readings (Pilot Test Data).   Figure 4, provided in Attachment A, shows the locations of the decontaminated areas (XRF Readings). 

On February 28, 2011 through March 2, 2011, START observed WGE contractors continue with the decontamination Pilot testing activities (Revised RAWP).  WGE contractors monitored air particulates while cleaning activities were being conducted (Air Monitoring Data).  There were sections of the warehouse pathway where concentrations were still above 400 ppm.  WGE contractors used a tavasco grinder on the floor and vacuumed dust with a high efficiency particulate air vacuum.  The areas of the previously covered pathway were screened and readings were below 400 ppm. 

Planned RP-Lead RA Activities

EPA tasked WGE with developing a Work Plan for remediating the remaining surface areas of concern in the warehouse while maintaining security to unqualified personnel for the area.  WGE will submit the Work Plan to the EPA OSC for approval and it will be incorporated into an upcoming time critical removal action under an Administrative Order on Consent (AOC).  Any further activities will be at the direction of the EPA OSC.

If you have any questions or comments regarding this letter report or require any additional information, please contact myself or Mr. Russell Henderson, START Assistant Program Manager, at 678-355-5550.

Sincerely,

Jerry Partap

START Project Manager