U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

LWD, Inc.

All POLREP's for this site LWD, Inc.
Calvert City, KY - EPA Region IV
POLREP #13
Printer Friendly  |   PDF
 
On-Scene Coordinator - Steve Spurlin 3/14/2007
Time-Critical - Removal Action Pollution Report (POLREP) #13
Start Date: 3/2/2006
Pollution Report (POLREP) #13
Site Description
Please refer to previous POLREPs for site description and previous actions taken.

Current Activities
The following activities took place during the reporting period:

Operation of the wastewater treatment system (WWT) was restarted on February 21, 2007.  Since restart, approximately 100,000 gallons of contaminated water have been treated.  To date, approximately 920,000 gallons have been treated by the WWT system.  Treated water is being used for decontamination operations and/or being land applied.

Containers of hazardous waste that remain on site are staged to prevent spills and are within containment areas.  




Planned Removal Actions
The following activities are planned during the next reporting period:

The WWT system will continue to be operated.  The treated water will be sampled and go through a lab analysis every 100,000 gallons before being land applied.  The most recent laboratory samples were collected on March 13.

Pumping of the liquid waste within the containment pit inside the incinerator building into frac tanks is planned.  Also, transportation and disposal of staged hazardous waste will be restarted by the potentially responsible party (PRP) group's contractors.  The PRP group's contractors are tentatively scheduled to take control of site activities on or around March 19.  





Next Steps
The following have been identified as next steps in the stabilization phase of this removal action:

Collected wastewater will continue to be treated.  The PRP group's contractors are tentatively scheduled to take control of site activities on or around March 19.  At this time, wastewater treatment will continue under the PRP's contractor control.


Key Issues
Weather conditions will continue to be monitored.  Temperatures below freezing may hamper operation of the WWT and thunderstorms will continue to hamper operation of the WWT system.

The PRP group's contractors are tentatively scheduled to take control of site activities on or around March 19.  The PRP's over-sight contractor is EnSafe and the project contractor is Veolia.