Peoples Gas 22nd Street Station Site

All POLREP's for this site Peoples Gas 22nd Street Station Site
Chicago, IL - EPA Region V
POLREP #31 - FINAL POLREP
Printer Friendly  |   PDF
 
On-Scene Coordinator - Tom Cook 7/29/2009
Time-Critical - Removal Action Pollution Report (POLREP) #31
Start Date: 6/18/2007 Completion Date: 4/30/2009
Site Description
See previous polreps for Site Description.

Current Activities
A summary of the activities performed during the reporting period by the PRP are as follows:
    
• Completed all planned excavation activities (see BMcD map of excavation areas under "documents" on OSC website);

• Transported 6 loads of soil to CID Landfill in Calumet City, IL; all trucks decontaminated prior to leaving site;

Transported 4 loads of soil to Countryside Landfill in Grayslake IL; all trucks decontaminated prior to leaving site;

• Completed backfilling of all areas;

• Completed final grading and restoration of the site;

• The water treatment system was cleaned and demobilized from the site;

• Perimeter real-time air monitoring was discontinued on March 13th, 2009 due to the completion of excavation activities.  Perimeter air sampling (24-hour air samples collected around the perimeter) utilizing PUF cartridges and Summa canisters was discontinued on March 23rd, 2009, with PM10 sampling continuing until the completion of grading activities.
  
• Performed health and safety air monitoring (using hand-held instruments in work zones) during site activities;

• Performed street sweeping activities on Racine Street and Cermak Road;

• Completed de-watering activities in excavation areas;

• Completed water treatment; and

• Discharged 203,800 gallons of treated water to the MWRD sanitary sewer.


START did not collect any split samples with the PRP during this reporting period.

On April 21, 2009, the final site walk through was conducted.  Attendees included the U.S. EPA OSC, representatives from Peoples Gas, START and the PRP contractor Burns & McDonnell.



Planned Removal Actions
Planned removal actions at the 22nd Street Station Site are as follows:

• There are no further planned removal actions at the 22nd Street Station Site, as the removal actions have been completed.


Next Steps
The next steps to be carried out by the PRP are as follows:

•    Submit Final Site Closure Report to the U.S. EPA.


Key Issues
None.

 
Disposition Of Wastes


Waste Stream Quantity Manifest # Disposal Facility
Non-hazardous Soil 10,440 yd3 March 2009 CID RDF, Calumet City, IL
Non-hazardous Soil 80.14 tons April 2009 Countryside Landfill, Grayslake, IL