This Polrep covers Site work performed from Sunday 11/8/09 through Friday 11/13/09.
Sunday 11/8/09 – no site work.
Monday 11/9/09 – no site work.
Tuesday 11/10/09 – no site work.
Wednesday 11/11/09 On-site today: 5 ERRS. Safety Meeting at 7:30am. Work ended at 5pm * Mobilized SCBA, pressure washer, 460 Excavator, Water Truck and Forklift to site. * Moved carbon out of GAC vessels and into cubic yard bags. Cleaned GAC vessels.
Thursday 11/12/09 On-site today: 5 ERRS. Safety Meeting at 7:30am. Work ended at noon. * Demobilized GAC vessels. * Level B entry into tank #1 to control vacuum truck hoses and remove sediment and water from tank. Three vacuum truck loads or sediment and water taken to Arlington landfill. * Deconned 460 Excavator and Water Truck. * Demobilized tank #1, Forklift, GAC vessels, pipe manifold and trench plates supporting GAC vessels. * Returned water meter to Clackamas county.
Friday 11/13/09 On-site today: 5 ERRS. Safety Meeting at 7:30am. Work ended at 5pm * Demobilized 460 Excavator, Water Truck, small equipment and crew. * Secured the site for the winter. This was the last day of site work for 2009.
Amend Action Memo and Task Order to transport remaining excavated soil off-site to appropriate landfill. Grade and seed bare areas.
|