Bremerton Gasworks

All POL/SITREP's for this site Bremerton Gasworks
Bremerton, WA - EPA Region X
POLREP #5
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Bremerton Gasworks - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region X

Subject: POLREP #5
Bremerton Gasworks
10JS
Bremerton, WA
Latitude: 47.5773250 Longitude: -122.6421064


To: Wally Moon, EPA Region 10 (POLREP List)

From: Kathy Parker, OSC
Date: 3/28/2012
Reporting Period:

1. Introduction
  1.1 Background
   
Site Number: 10JS    Contract Number:  
D.O. Number:      Action Memo Date:  
Response Authority: CERCLA    Response Type: Emergency
Response Lead: EPA    Incident Category: Removal Action
NPL Status: Non NPL    Operable Unit: Beach
Mobilization Date: 10/5/2010    Start Date: 10/5/2010
Demob Date:      Completion Date:  
CERCLIS ID: WAN001002907    RCRIS ID:
ERNS No.:    State Notification:
FPN#:    Reimbursable Account #:

2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative

2.1.2 Response Actions to Date

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
On 3/26/2012 Chris Field, Wally Moon, Bill Ryan, Kathy Parker and Elizabeth McKenna met to discuss the status of the SOW for the Cascade Natural Gas AOC.  The decision was made to separate the removal evaluation tasks in the SOW from the remedial tasks in order to have the PRP perform the removal avtion tasks as soon as possible. Kathy checked the tide tables and determined the sampling of the beach must start June 2 and the Removal Action must start July 28, 2012 in order to take advantage of low day-time tides on the beach.  Elizabeth agreed to talk to Howard, the PRP attorney, about separating the SOW and expediting the approval process.


2.1.4 Progress Metrics

Waste Stream Medium Quantity Manifest # Treatment Disposal
           
           
           


  2.2 Planning Section
    No information available at this time.

  2.3 Logistics Section
    No information available at this time.

  2.4 Finance Section
   
   
Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $25,000.00 $5,000.00 $20,000.00 80.00%
START $32,000.00 $9,000.00 $23,000.00 71.88%
Intramural Costs
 
Total Site Costs $57,000.00 $14,000.00 $43,000.00 75.44%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


  2.5 Other Command Staff
    No information available at this time.

3. Participating Entities
  No information available at this time.

4. Personnel On Site
  No information available at this time.

5. Definition of Terms
  No information available at this time.

6. Additional sources of information
  No information available at this time.

7. Situational Reference Materials
  No information available at this time.

POLREP #5 Last Updated 9/5/2017