U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portage Creek Area

All POL/SITREP's for this site Portage Creek Area
Kalamazoo, MI - EPA Region V
POLREP #37
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Portage Creek Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #37
Progress
Portage Creek Area
059B05
Kalamazoo, MI
Latitude: 42.2839750 Longitude: -85.5791570


To: Sam Borries, U.S. EPA
Jason El-Zein, U.S. EPA
John Maritote, U.S. EPA
Mike Ribordy, U.S. EPA
Mark Mills, Michigan DNR
Daria Devantier, MDEQ
Paul Bucholtz, MDEQ
Debbie Jung, City of Kalamazoo
Lisa Williams, U.S. FWS
Todd Goeks, NOAA
Valincia Darby, Department of Interior
Mark Johnson, ATSDR

From: Craig Thomas, On-Scene Coordinator
Date: 10/11/2013
Reporting Period: 9/28/2013 - 10/11/2013

1. Introduction
  1.1 Background
   
Site Number: 059B05    Contract Number: EP-S5-08-02
D.O. Number: 0087    Action Memo Date: 7/5/2011
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: EPA    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 05
Mobilization Date: 9/26/2011    Start Date: 8/30/2011
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID: NA
ERNS No.:    State Notification: Yes
FPN#:    Reimbursable Account #:

1.1.1 Incident Category
Fund-lead removal action

1.1.2 Site Description
See POLREP #1

1.1.2.1 Location
See POLREP #1

1.1.2.2 Description of Threat
See POLREP #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
See POLREP #1

2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative
Backfilling and re-construction of the creek channel and banks was completed in SA1A.  All equipment, supplies and materials are being demobilized from SA1A and SA1B support areas. Contaminated sediments excavated from SA1A have been shipped for disposal to an approved facility.

2.1.2 Response Actions to Date
From September 28 to October 11, EPA and ERRS contractors conducted the following activities:

Site Activities - John Street Staging Area
- Treated 14,321 gallons of potentially contaminated contact water in EPA's mobile wastewater treatment plant, for a total of 1,120,456 gallons treated to date; 
- Loaded out 2,262 tons of TSCA-contaminated sediments for transport & disposal at an approved landfill facility;
- Received, decontaminated, wipe sampled and demobilized heavy equipment; and
- Conducted work area perimeter air monitoring for dust.

Site Activities - SA1A
- Received and stockpiled aggregrates to support backfilling operations;
- Completed final backfilling of grids SA1A-1 to SA1A-9 according to Restoration Plan;
- Removed and demobilized isolation (groundwater) dewatering system;
- Removed and demobilized upstream and downstream sheet pile coffer dams;
- Conducted bank stabilization, restoration and temporary seeding;
- Began removing staging and support area equipment, materials and supplies; and
- Conducted work area perimeter air monitoring for dust.

Site Activities - SA1B
- Removed and demobilized creek bypass pumps
- Began demobilizing staging and support area equipment, materials and supplies; and
- Began re-construction, stabilization, restoration and temporary seeding of area.

Project Management Activities
- Continued weekly progress meetings with City of Kalamazoo, including property owners upon request;
- Conducted landscaping maintenance & irrigation in Rose Park;
- Finalized plans for temporary restoration of John Street staging pad in coordination with property owners;
- Finalized plans to re-construct sections of KRVT boardwalk removed for bypass pumping system;
- Finalized plans for re-opening of KRVT closed due to project in late October;
- Finalized plan for restoration of SA1C (west bank) with property owner;
- Finalized development of site specific restoration plans for SA1A; and
- Continued development of project final report.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
See POLREP #1

2.1.4 Progress Metrics
 
Waste Stream Medium Quantity Manifest # Treatment Disposal
TSCA contaminated
sediments
solidified sediment  2262 tons 010588962JJK-010588963JJK;
010331410JJK-010331455JJK 
disposal  Wayne Disposal,
Belleville, MI 
 Tires rubber  51  NA recycling  Entech, Inc.,
White Pigeon, MI 
Shipping Pallets wood 120 none reuse Allen Trench Safety 

 

  2.2 Planning Section
    Removal activities anticipated to take place from October 12 to October 25 include the following:
 
Site Activities - John Street Staging Area
- Complete treatment of contact water from the staging pad sump with mobile wastewater treatment plant;
- Decontaminate, wipe sample and demobilize remaining heavy equipment;
- Conduct post-construction soil sampling in staging and support areas;
- Remove 'trucks entering highway' signs from Crosstown Parkway;
- Remove staging pad for disposal at approved landfill facility and re-grade area;
- Prepare for demobilization of trailers and offices; and
- Conduct work area perimeter air monitoring for dust.

Site Activities - SA1A
- Remove remaining equipment from staging area(s);
- Remove and cut bypass pump system piping from Rose Park and ship back to vendor;
- Re-construct KRVT decking on boardwalk removed for bypass pump system piping;
- Replace light post removed from Rose Park removed for bypass pump system piping;
- Conduct post-construction sampling in staging and support areas;
- Remove all fencing and rock from staging area(s); and
- Complete temporary restoration and seeding of staging area(s).

Site Activities - SA1B
- Remove remaining equipment from staging area;
- Restore creek bank used for bypass pumping system pump pad.
- Remove temporary fencing; and
- Complete temporary restoration and seeding of staging area.

Project Management Activities
- Continue weekly progress meetings with City of Kalamazoo, including property owners upon request;
- Continue weekly landscaping maintenance & irrigation in Rose Park;
- Conduct post-construction structure features assessment in SA1;
- Identify all damaged sidewalk and pavement damages due to project activities and solicit bids for repairs; and
- Solicit bids for final restoration work according to area-specific restoration plans in SA1.

2.2.1 Anticipated Activities
See POLREP #2

2.2.1.1 Planned Response Activities
See above

2.2.1.2 Next Steps
See above

2.2.2 Issues
None

  2.3 Logistics Section
   

The current resources present on site during this reporting period include:

- Office trailers
- Portable restrooms & hand-washing stations
- Portable generators
- Submersible pumps
- Tire Wash decon pad
- Equipment storage container
- ERRS work crews and subcontractor work crews
- START sampling contractor
- Security subcontractor personnel
- Heavy equipment
- Water truck
- Street sweeper
- Frac (water) tanks
- Pressure wash trailer
- Bypass pumps & piping
- Sheet piling
- Mobile wastewater treatment plant

- Monitoring equipment
- Traffic control structures & roadway signage
- Mobile light towers
- Crane and operator
- Bypass pump subcontractor personnel


  2.4 Finance Section
    2.4.1 Narrative
See table

   
Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $13,300,000.00 $10,313,028.00 $2,986,972.00 22.46%
TAT/START $700,000.00 $479,683.00 $220,317.00 31.47%
Intramural Costs
 
Total Site Costs $14,000,000.00 $10,792,711.00 $3,207,289.00 22.91%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


  2.5 Other Command Staff
    2.5.1 Safety Officer

Craig Thomas, Paul Ruesch and Andy Maguire serve as safety officer(s). The HASP is reviewed and signed by all site personnel. All new personnel, including sub-contractors, are provided a site orientation and safety briefing. Safety meetings are held each morning with all site workers.

2.6 Liaison Officer
Craig Thomas, Paul Ruesch and Andy Maguire serve as liaison(s) with local officials and interested parties.

2.7 Information Officer
A site tour & interview was provided to a reporter and photographer from Connect, a monthly television show on the Public Media Network on October 1.  A 1 hour presentation on the project was provided to 25 students of the Michigan Conservation Stewards Program at the Kalamazoo Nature Center on October 3.  A telephone interview was provided to Michigan Public Radio (October 7).
 
2.7.1 Public Information Officer
See Section 2.6

Signage was ordered to alert KVRT users of the trail re-opening. The signs will be placed along the KVRT when it is re-opened later this month.

2.7.2 Community Involvement Coordinator
Don DeBlasio - U.S. EPA


3. Participating Entities
  3.1 Unified Command
N/A

3.2 Cooperating Agencies

U.S. Environmental Protection Agency

Michigan Department of Environmental Quality
Michigan Department of Agriculture and Rural Development

Michigan Department of Natural Resources

U.S. Fish and Wildlife Service

City of Kalamazoo:

            Department of Public Services
            Parks and Recreation Department
            Economic Development Department
            Community Planning & Development
            Public Safety Department
            Fire Department
            Police Department
            Redevelopment Department
Bronson Methodist Hospital

Kalamazoo Nature Center


4. Personnel On Site
 

U.S. EPA - 2
START contractor (Weston Solutions) - 1
ERRS contractor (Environmental Quality Management, Inc) - 12
Fulton Trucking - 2
S&K Trucking - 4
Jackson-Merkey Contractors, Inc. - 3
Rain for Rent - 4
Grand Davo Crane Contractors 2
Baker Pumps - 1

TOTAL PERSONNEL = 30


5. Definition of Terms
  ERRS - Emergency and Rapid Response Services
FOSC - Federal On Scene Coordinator
U.S. FWS - United States Fish and Wildlife Service
HASP - Health and Safety Plan
KRVT - Kalamazoo River Valley Trail
mg/kg - milligrams per kilogram
mg/m3 - milligrams per cubic meter
MDEQ - Michigan Department of Environmental Quality
NA - Not Applicable
NOAA - National Oceanic and Atmospheric Administration
NPL - National Priorities List
NRDA - Natural Resource Damage Assessment
PCB - polychlorinated biphenyl
ppm - parts per million
PRPs - Potentially Responsible Parties
RTK GPS - Real Time Kinematic Global Positioning System
SA - Slope Area
START - Superfund Technical Assessment and Response Team
U.S. EPA - United States Environmental Protection Agency

6. Additional sources of information
  6.1 Internet location of additional information/report

See the project website at http://www.epaosc.org/portagecreekarea.


6.2 Reporting Schedule
The next POLREP will be generated on October 25.

7. Situational Reference Materials
 

See the project website at http://www.epaosc.org/portagecreekarea

Additional information on the overall Kalamazoo River Project can be found at http://www.epa.gov/Region5/cleanup/kalproject/index.htm.


POLREP #37 Last Updated 11/19/2014

Click here to view Attached Images