2.1.1 Narrative
On July 13, 2015, EPA mobilized equipment and personnel to the Site to began a time critical removal action to address threats from asbestos roofing tiles. The scope of the removal involves the physical removal of the tiles that remain attached to the roof, and the tiles that have fallen inside and outside the building. Project duration is estimated at six weeks.
2.1.2 Response Actions to Date
July 20 to July 25, 2015
· The ERRS contractor conducted site preparation activities to include removal and recycling of scrap metal, installation of barrier marking work zone, and building of decontamination unit.
· The ERRS contractor conducted removal activities to include the following:
o Demolition of the small office located near the southeast corner of the north building.
o Removal of asbestos-contaminated debris from inside and around the outside of the north building.
o Removal of fire damaged equipment and metal from the inside and around the outside of the north building.
o Water trucks were used for dust suppression during demolition and removal activities and to wash metal recovered for recycling.
· Tetra Tech START conducted initial background and perimeter air sampling and soil sampling of two locations not sampled during the previous site assessment.
· Background perimeter air sampling was conducted at one onsite location and at three residential locations prior to removal activities. The result for the onsite location was 0.0017 f/cc and the results for the residential locations ranged from 0.0010 f/cc to 0.0017 f/cc. Samples were identified and analyzed via transmission electron microscopy to be reported in a PCM-equivalent. Results from the TEM analysis were not yet received.
· Area perimeter air sampling was conducted at one onsite location and at three residential locations during removal activities. Results for the onsite location ranged from 0.0020 to 0.0033 f/cc and the results for the residential locations ranged from 0.0014 f/cc to 0.0022 f/cc. Samples were identified and analyzed via transmission electron microscopy to be reported in a PCM-equivalent. Results from the TEM analysis were not yet received.
· Seven loads of metal have been sent of site for recycling this week for a total of approximately 76 tons.
· Nine 20 cubic yard roll offs of asbestos-contaminated debris were transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period.
July 27 to August 1, 2015
· The ERRS contractor conducted removal activities to include the following:
o Conducted a surface soil scrape of the area north of the north building to stage brick demolition debris.
o Conducted demolition of the north building. Demolition debris was visually inspected by a State of Tennessee accredited asbestos project monitor. Debris that appeared to be mixed with asbestos-containing roofing material was loaded into roll off boxes lined with two layers of 6-mil plastic sheeting for disposal at a State of Tennessee approved asbestos landfill. Debris that did not appear to be mixed with asbestos-containing roofing material was staged in the area north of the north building.
o Scraped and washed the concreted deck inside the north building prior to demolition of the north, northeast, and northwest brick walls to ensure the brick was not contaminated by asbestos debris and could be staged at the area north of the north building.
o Conducted surface scraping of gross asbestos-contaminated debris inside the south building.
o Removed, washed, staged, and recycled structural steel and other metal retrieved during demolition of the north building.
o Water trucks were used for dust suppression during demolition, removal, and recycling activities.
· The START contractor conducted area perimeter air sampling at one onsite location and at three residential locations during removal activities. Results for the onsite location ranged from 0.0018 to 0.0043 f/cc and the results for the residential locations ranged from 0.0010 f/cc to 0.0037 f/cc. TEM results for two background locations sampled on 7/20/15 indicated there were no asbestos fibers detected and the asbestos fiber concentrations were less than the limit of detection.
· Four loads of metal totaling approximately 27 tons have been sent off site for recycling this week. To date, a total of 11 loads of metal have been recycled for a total of approximately 103 tons.
· Seventeen 20 cubic yard roll offs of asbestos-contaminated debris were transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period. To date, a total of 26, 20 cubic yard roll offs have been transported to the landfill for disposal.
August 3 to August 8, 2015
· The ERRS contractor conducted removal activities to include the following:
o Finished demolition of the north building. Demolition debris was visually inspected by a State of Tennessee accredited asbestos project monitor. Debris that appeared to be mixed with asbestos-containing roofing material was loaded into roll off boxes lined with two layers of 6-mil plastic sheeting for disposal at a State of Tennessee approved asbestos landfill. Debris that did not appear to be mixed with asbestos-containing roofing material was staged in the area north of the north building.
o Scraped and washed the concreted deck inside the north building prior to demolition of the south and southeast brick walls to ensure the brick was not contaminated by asbestos debris and could be staged at the area north of the north building.
o Conducted surface scraping of gross asbestos-contaminated debris inside the south building.
o Scraped and washed the concreted deck outside the south building prior to demolition of the north and northeast brick walls to ensure the brick was not contaminated by asbestos debris and could be staged at the area north of the north building.
o Removal of asbestos containing roof shingles from the east roof of the south building.
o Removed, washed, staged, and recycled structural steel and other metal retrieved during demolition of the north and south buildings.
o Water trucks were used for dust suppression during demolition, removal, and recycling activities.
· The START contractor conducted area perimeter air sampling at one onsite location and at three residential locations during removal activities. Results for the onsite location ranged from 0.0014 to 0.0089 f/cc (08/03/15 to 08/05/15) and the results for the residential locations ranged from <0.00082 f/cc (below limit of detection) to 0.0014 f/cc (08/03/15 to 08/05/15). TEM results for samples collected on 7/30/15, indicated there were no asbestos fibers detected and the asbestos fiber concentrations were less than the limit of detection.
· Six loads of metal have been sent off site for recycling this week. As of now we only have the weight of the first 3 loads of metal, which add up for a total of approximately 24 tons. To date, a total of 17 loads of metal have been recycled for a total of approximately 127 tons (excluding the weight of the last 4 loads).
· Thirty-two 20 cubic yard roll offs of asbestos-contaminated debris were transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period. To date, a total of 58, 20 cubic yard roll offs have been transported to the landfill for disposal.
August 10 to August 15, 2015
· The ERRS contractor conducted removal activities to include the following:
o Debris that appeared to be mixed with asbestos-containing roofing material was loaded into roll off boxes lined with two layers of 6-mil plastic sheeting for disposal at a State of Tennessee approved asbestos landfill. Brick that did not appear to be mixed with asbestos-containing roofing material was staged in the area north of the north building or used to fill in the small ditch area outside the southeast side of the south building.
o Conducted surface scraping of asbestos-contaminated debris inside the south building.
o Scraped and washed the concreted deck outside the south building prior to demolition of the north brick wall to ensure the brick was not contaminated by asbestos debris and could be staged at the area north of the north building.
o Removal of metal roof shingles from the east roof of the south building.
o Scraped top layer of soil and washed the concreted deck outside the south building prior to demolition of the east/southeast brick wall to ensure the brick would not fall onto asbestos debris outside of the south building during demolition of the east/southeast wall.
o Used clean brick from south and east/southeast walls of the south building to fill in the loading dock depression area outside the southeast side of the south building.
o Demolished the west, northwest and southwest walls of the south building and loaded debris into roll off boxes lined with two layers of 6-mil plastic sheeting for disposal at a State of Tennessee approved asbestos landfill.
o Torched notches in the 2 rows of columns to weaken and aid the demolition of the entire frame.
o Pulled down the entire frame of the south building using 2 excavators with cables attached.
o Removed, washed, staged, and recycled structural steel and other metal retrieved during demolition of the south building.
o A water truck was used for dust suppression during demolition, removal, and recycling activities.
· The START contractor conducted area perimeter air sampling at one onsite location and at three residential locations during removal activities. Results for the onsite location from the only day we have results from as of now were 0.0025(equal to the limit of detection) and 0.0010 f/cc (08/11/15) and the results for the residential locations ranged from <0.00085 f/cc (below limit of detection) to 0.00094 f/cc (08/11/15).
· Five loads of metal have been sent off site for recycling this week. To date, a total of 20 loads of metal have been recycled for a total of approximately 168 tons.
· Twenty-two 20 cubic yard roll offs of asbestos-contaminated debris were transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period. To date, a total of 81, 20 cubic yard roll offs have been transported to the landfill for disposal.
August 17, 2015 to August 22, 2015
- The ERRS contractor conducted removal activities to include the following:
- Removed, staged, loaded, and recycled structural steel from the frame of the south building.
- Removed asbestos-contaminated debris from on and around the footprint of the south building. The debris was staged for disposal.
- Scraped asbestos-contaminated soil from identified areas south of the south building.
- Conducted a surface scrape of the soil along the access road located on the east side of the site.
- A water truck was used for dust suppression during demolition, removal, and recycling activities.
- The START contractor performed visual inspections of the soil scraped areas located at the southern end of the site and along the west side of the north building. Areas where asbestos-containing materials remained visible were identified to the ERRS contractor for additional scraping.
- The START contractor collected a composite soil sample from the grid area located between the west side of the north building and the silt fence. The soil was shipped to the laboratory and analyzed for asbestos.
- The START contractor conducted area perimeter air sampling at one onsite location and at three residential locations during removal activities. Results for those samples collected on 8/12/15 for the onsite location ranged from <0.0028 f/cc to <0.00085 f/cc and the results for the residential locations ranged from <0.00085 f/cc (below limit of detection) to 0.00110 f/cc. TEM results for samples collected on 7/29/15 and 7/31/15 indicated there were no asbestos fibers detected and the asbestos fiber concentrations were less than the limit of detection.
- Nine loads of metal have been sent off site for recycling this week. A total of 29 loads of metal have been recycled through 8/22/15 for a total of approximately 296 tons (tons recycled totaled through 8/21/15).
Thirty, 20 cubic yard roll offs of asbestos-contaminated debris were transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period. To date, a total of 111, 20 cubic yard roll offs for an estimated 2,220 cubic yards of asbestos-contaminated waste have been transported to the landfill for disposal.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
This is a fund lead time critical removal action.
2.1.4 Progress Metrics
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| asbestos |
roof tile |
111 rolloffs
(20 cubic yards/rolloff) |
see waste tracking
spreadsheet in Documents
section of website |
landfill |
Waste Management-West Camden Sanitary landfill |
| |
|
|
|
|
|
| |
|
|
|
|
|
.
Thirty, 20 cubic yard roll offs of asbestos-contaminated debris were transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period. To date, a total of 111, 20 cubic yard roll offs for an estimated 2,220 cubic yards of asbestos-contaminated waste have been transported to the landfill for disposal.This is a fund lead time critical removal action. .
|