2.1.1 Narrative
On July 13, 2015, EPA mobilized equipment and personnel to the Site to began a time critical removal action to address threats from asbestos roofing tiles. The scope of the removal involved the physical removal of the tiles that remain attached to the roof, and the removal of tiles that have fallen inside and outside the buildings.
2.1.2 Response Actions to Date
July 13 to July 25, 2015
· The ERRS contractor conducted site preparation activities to include placing job trailers, removing and recycling of scrap metal, installation of barrier marking work zone, and building of decontamination unit.
· The ERRS contractor conducted removal activities to include the following:
o Demolition of the small office located near the southeast corner of the north building.
o Removal of asbestos-contaminated debris from inside and around the outside of the north building.
o Removal of fire damaged equipment and metal from the inside and around the outside of the north building.
o Water trucks were used for dust suppression during demolition and removal activities and to wash metal recovered for recycling.
· Tetra Tech START conducted initial background and perimeter air sampling and soil sampling of two locations not sampled during the previous site assessment.
· Background perimeter air sampling was conducted at one onsite location and at three residential locations prior to removal activities.
· Seven loads of metal were sent of site for recycling during this period.
· Nine 20 cubic yard roll offs of asbestos-contaminated debris were transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period.
July 27 to August 1, 2015
· The ERRS contractor conducted removal activities to include the following:
o Conducted a surface soil scrape of the area north of the north building to stage brick demolition debris.
o Conducted demolition of the north building. Demolition debris was visually inspected by a State of Tennessee accredited asbestos project monitor. Debris that appeared to be mixed with asbestos-containing roofing material was loaded into roll off boxes lined with two layers of 6-mil plastic sheeting for disposal at a State of Tennessee approved asbestos landfill. Debris that did not appear to be mixed with asbestos-containing roofing material was staged in the area north of the north building.
o Scraped and washed the concreted deck inside the north building prior to demolition of the north, northeast, and northwest brick walls to ensure the brick was not contaminated by asbestos debris and could be staged at the area north of the north building.
o Conducted surface scraping of gross asbestos-contaminated debris inside the south building.
o Removed, washed, staged, and recycled structural steel and other metal retrieved during demolition of the north building.
o Water trucks were used for dust suppression during demolition, removal, and recycling activities.
· The START contractor conducted area perimeter air sampling at one onsite location and at three residential locations during removal activities.
· Four loads of metal were sent off site for recycling. To date, a total of 11 loads of metal have been recycled for a total of approximately 103 tons.
· Seventeen 20 cubic yard roll offs of asbestos-contaminated debris were transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period. To date, a total of 26, 20 cubic yard roll offs have been transported to the landfill for disposal.
August 3 to August 8, 2015
· The ERRS contractor conducted removal activities to include the following:
o Finished demolition of the north building. Demolition debris was visually inspected by a State of Tennessee accredited asbestos project monitor. Debris that appeared to be mixed with asbestos-containing roofing material was loaded into roll off boxes lined with two layers of 6-mil plastic sheeting for disposal at a State of Tennessee approved asbestos landfill. Debris that did not appear to be mixed with asbestos-containing roofing material was staged in the area north of the north building.
o Scraped and washed the concreted deck inside the north building prior to demolition of the south and southeast brick walls to ensure the brick was not contaminated by asbestos debris and could be staged at the area north of the north building.
o Conducted surface scraping of gross asbestos-contaminated debris inside the south building.
o Scraped and washed the concreted deck outside the south building prior to demolition of the north and northeast brick walls to ensure the brick was not contaminated by asbestos debris and could be staged at the area north of the north building.
o Removal of asbestos containing roof shingles from the east roof of the south building.
o Removed, washed, staged, and recycled structural steel and other metal retrieved during demolition of the north and south buildings.
o Water trucks were used for dust suppression during demolition, removal, and recycling activities.
· The START contractor conducted area perimeter air sampling at one onsite location and at three residential locations during removal activities. Six loads of metal have been sent off site for recycling this week. Thirty-two 20 cubic yard roll offs of asbestos-contaminated debris were transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period. To date, a total of 58, 20 cubic yard roll offs have been transported to the landfill for disposal.
August 10 to August 15, 2015
· The ERRS contractor conducted removal activities to include the following:
o Debris that appeared to be mixed with asbestos-containing roofing material was loaded into roll off boxes lined with two layers of 6-mil plastic sheeting for disposal at a State of Tennessee approved asbestos landfill. Brick that did not appear to be mixed with asbestos-containing roofing material was staged in the area north of the north building or used to fill in the small ditch area outside the southeast side of the south building.
o Conducted surface scraping of asbestos-contaminated debris inside the south building.
o Scraped and washed the concreted deck outside the south building prior to demolition of the north brick wall to ensure the brick was not contaminated by asbestos debris and could be staged at the area north of the north building.
o Removal of metal roof shingles from the east roof of the south building.
o Scraped top layer of soil and washed the concreted deck outside the south building prior to demolition of the east/southeast brick wall to ensure the brick would not fall onto asbestos debris outside of the south building during demolition of the east/southeast wall.
o Used clean brick from south and east/southeast walls of the south building to fill in the loading dock depression area outside the southeast side of the south building.
o Demolished the west, northwest and southwest walls of the south building and loaded debris into roll off boxes lined with two layers of 6-mil plastic sheeting for disposal at a State of Tennessee approved asbestos landfill.
o Torched notches in the 2 rows of columns to weaken and aid the demolition of the entire frame.
o Pulled down the entire frame of the south building using 2 excavators with cables attached.
o Removed, washed, staged, and recycled structural steel and other metal retrieved during demolition of the south building.
o A water truck was used for dust suppression during demolition, removal, and recycling activities.
· The START contractor conducted area perimeter air sampling at one onsite location and at three residential locations during removal activities. Five loads of metal have been sent off site for recycling this week. To date, a total of 20 loads of metal totalling approximately 168 tons have been shipped for recycle.
· Twenty-two 20 cubic yard roll offs of asbestos-contaminated debris were transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period. To date, a total of 81, 20 cubic yard roll offs have been transported to the landfill for disposal.
August 17, 2015 to August 22, 2015
- The ERRS contractor conducted removal activities to include the following:
- Removed, staged, loaded, and recycled structural steel from the frame of the south building.
- Removed asbestos-contaminated debris from on and around the footprint of the south building. The debris was staged for disposal.
- Scraped asbestos-contaminated soil from identified areas south of the south building.
- Conducted a surface scrape of the soil along the access road located on the east side of the site.
- A water truck was used for dust suppression during demolition, removal, and recycling activities.
- The START contractor performed visual inspections of the soil scraped areas located at the southern end of the site and along the west side of the north building. Areas where asbestos-containing materials remained visible were identified to the ERRS contractor for additional scraping.
- The START contractor collected a composite soil sample from the grid area located between the west side of the north building and the silt fence. The soil was shipped to the laboratory and analyzed for asbestos.
- The START contractor conducted area perimeter air sampling at one onsite location and at three residential locations during removal activities.
- Nine loads of metal have been sent off site for recycling this week. A total of 29 loads of metal have been recycled through 8/22/15.
- Thirty, 20 cubic yard roll offs of asbestos-contaminated debris were transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period. To date, a total of 111, 20 cubic yard roll offs for an estimated 2,220 cubic yards of asbestos-contaminated waste have been transported to the landfill for disposal.
August 24 to August 28, 2015
The ERRS contractor conducted removal activities to include the following:
- Completed loading and recycling of structural steel from the south building.
o Removed asbestos-contaminated debris from the footprint of the south building.
o Scraped asbestos-contaminated soil from areas south and west of the south building
o Scraped and washed the residual asbestos-contaminated material from all building areas
o Conducted a surface scrape of the soil along the north side of the access road
The START contractor performed visual inspections of the soil scraped areas located at the northern, southern, and western ends of the site. Areas where asbestos-containing materials remained visible were identified to the ERRS contractor for additional scraping. The START contractor collected composite soil samples from the grid areas located on the north, south, east, and west sides of the site. The soil was shipped to the laboratory and analyzed for asbestos. Soil sampling results from 8/20/15, 8/24/15, and 8/25/15 comprising eight grid locations ranged from 0.5% to 5.25% chrysotile asbestos.· The START contractor conducted area perimeter air sampling at one onsite location and at three residential locations during removal activities. Two loads of metal were sent off site for recycling this week. A final total of 31 loads of metal have been recycled through 8/24/15.· Thirty-one 20 cubic yard roll offs of asbestos-contaminated debris were transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period. To date, a total of 142, 20 cubic yard roll offs for an estimated 2,840 cubic yards of asbestos-contaminated waste have been transported to the landfill for disposal.
August 31 to September 4, 2015
The ERRS contractor conducted removal and backfilling activities to include the following:
o Completed removal of asbestos-contaminated debris from on and around the north end of the footprint of the south building. The debris was loaded and transported for disposal.
o Completed washing the residual asbestos-contaminated debris from the footprint of the south building and the alley way between the north and south buildings.
o Completed backfilling and capping of all soil-scraped areas on site.
o Decontaminated and demobilized site equipment.·
The START contractor performed visual inspections of the building footprints. No visible asbestos-containing materials was observed. The START contractor collected a total of 17 composite soil samples from 7/21/15 to 8/26/15 that ranged from 0.5% to 5.25% chrysotile asbestos and 0.25% amosite asbestos The START contractor collected at total of 114 area perimeter air samples during the removal. No asbestos was detected in any air samples. One 20 cubic yard roll off of asbestos-contaminated debris was transported from the site to a State of Tennessee approved asbestos landfill for disposal during this time period. For the removal, a final total of 143, 20 cubic yard roll offs, for an estimated 2,860 cubic yards of asbestos-contaminated waste, have been transported to the landfill for disposal.· The ERRS and START contractors demobilized from the site.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
This is a fund lead time critical removal action.
2.1.4 Progress Metrics
-
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| asbestos containing material |
roof tile, debris, and soil |
143 rolloffs
(20 cubic yards/rolloff) |
see waste tracking
spreadsheet in Documents
section of website |
landfill |
Waste Management-West Camden Sanitary landfill, Camden, TN |
| |
|
|
|
|
|
| |
|
|
|
|
|
.
|