National Petroleum Packers

All POL/SITREP's for this site National Petroleum Packers
Stallings, NC - EPA Region IV
POLREP #8
Warehouse drums removed, demolition of ASTs begin
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
National Petroleum Packers - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region IV

Subject: POLREP #8
Warehouse drums removed, demolition of ASTs begin
National Petroleum Packers
A4QL
Stallings, NC
Latitude: 35.0847089 Longitude: -80.6782999


To:
From: Jeffery Crowley, OSC
Date: 12/13/2010
Reporting Period: 12/3/2010 - 12/11/2010

1. Introduction
  1.1 Background
   
Site Number: A4QL    Contract Number: EP-S4-07-04
D.O. Number: 105    Action Memo Date: 9/14/2010
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: EPA    Incident Category: Removal Action
NPL Status: Non NPL    Operable Unit:
Mobilization Date: 9/29/2010    Start Date: 9/29/2010
Demob Date:      Completion Date:  
CERCLIS ID: NCD986232213    RCRIS ID:
ERNS No.:    State Notification: 03/12/2010
FPN#:    Reimbursable Account #:

1.1.1 Incident Category
Inactive Waste Management Facility.
1.1.2 Site Description
For Site Description, location, and description of threat please refer to previous POLREPs.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
For detailed information on the Preliminary Removal Assessment and Site Inspection please refer to the Removal Site Evaluation POLREP (POLREP #2) and the the RSE Site Evaluation Report (2007).


2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative

As stated earlier, the Site had a previous Removal Site Evaluation conducted by EPA in June, July, and August of 2007.  Detailed information on that RSE can be found in POLREP #1 and in the Final RSE Report submitted 11/21/2007.  However, a review of that data concludes that the threats posed still remain. After a review of the data generated from the previous site evaluation and the current site condition, ERRB concluded that the site met the criteria as set forth in 40 CFR 300.415 (b)(2) for a time critical removal action.  An Action Memorandum was signed on September 10, 2010 to initiate a time-critical removal action at the Site.

2.1.2 Response Actions to Date

The following actionstook place during this reporting:

  • ERRS continued to pump out the ASTs on site.  During this reporting period 17 loads of material were shipped off site for an approximate total volume of 79,000 gallons removed during this reporting period and 227,000 gallons total. Temperature continues to be an issue on site as the recent sub-freezing temperatures are causing the hoses and liquids to freeze or become very viscous. 
  • Two truckloads (70 and 54 drums respectively) were also loaded and shipped off the site on 12/6/10.  These drums contained Non-DOR/Non-RCRA Waste, waste sodium hydroxide, and 28 lab packs.  Removal of these drums completes cleanup activities of the chemicals from the warehouse, lab, and lab closet.  This brings the total drums count to 323 with 4 pallets of solid materials and 8 compressed gas cylinders removed from the Site.
  • ERRS began demolition of the ASTs on 12/9/10. During this reporting period, three tanks were demolished.  Tanks are being cut into 10 foot sections, then are decontaminated, then placed into storage boxes.  The steel from the tanks in then sent to a metal recycler.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

Enforcement activities are ongoing.


  2.2 Planning Section
    2.2.1 Anticipated Activities

    2.2.1.1 Planned Response Activities

During the next reporting period it is anticipated that the removal of materials from and demolition of the ASTs will continue. Crews will work until 12/21/10 and then demobilize from the Site for the Holidays.  work will resume on-site on 1/4/11.


    2.2.1.2 Next Steps

Once back from the Holiday break, demolition will continue on the ASTs.  


2.2.2 Issues

Temperature continues to be an issue.  As the temperature drops some of the sludgy materials in the ASTs has become harder to pump.  


  2.3 Logistics Section
    At this time, this Site poses no logistical issues.

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    No information available at this time.

3. Participating Entities
  No information available at this time.

4. Personnel On Site
  Maximum staffing during this reporting period:

1 - EPA OSC
2 - START (Otie)
5 - ERRS (ER)

5. Definition of Terms
  AST - Above Ground Storage Tank
BTU - British Thermal Unit
CI - Civil Investigator
EPA - Environmental Protection Agency
EPM - Enforcement Project Manager
ERRB - Emergency Response and Removal Branch
ERRS - Emergency and Rapid Response Services
NFPA - National Fire Protection Association
NPP - National Petroleum Packers
OSC - On Scene Coordinator
PPE - Personal Protective Equipment
PRP - Potentially Responsible Party
RFQ - Request For Quote
START - Superfund Technical Assessment and Response Team


6. Additional sources of information
  No information available at this time.

7. Situational Reference Materials
  No information available at this time.