1. Introduction
|
|
|
1.1 Background
|
|
|
|
|
Site Number: |
02XY |
|
Contract Number: |
|
|
D.O. Number: |
|
|
Action Memo Date: |
|
|
Response Authority: |
CERCLA |
|
Response Type: |
Emergency |
|
Response Lead: |
PRP |
|
Incident Category: |
Removal Action |
|
NPL Status: |
Non NPL |
|
Operable Unit: |
|
|
Mobilization Date: |
11/15/2010 |
|
Start Date: |
11/15/2010 |
|
Demob Date: |
|
|
Completion Date: |
|
|
CERCLIS ID: |
NJN000205896 |
|
RCRIS ID: |
|
|
ERNS No.: |
|
|
State Notification: |
11/30/2010 |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Abandoned Building containing friable asbestos.
1.1.2 Site Description
See Polrep 1.
1.1.2.1 Location
See Polrep 1.
1.1.2.2 Description of Threat
See Polrep 1.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
|
|
2. Current Activities
|
|
|
2.1 Operations Section
|
|
|
|
2.1.1 Narrative
The PRP is funding and subcontracting the asbestos abatement work.
2.1.2 Response Actions to Date
Since the last reporting period the following events have occurred: The air clearance testing of the main building was conducted on December 7, 2010. The analytical results were reported to the asbestos abatement subcontractor on December 8, 2010. All air clearance analytical results were reportedly below the regulatory levels indicating the building has passed the air clearance test. Although the asbestos abatement prime contractor stated that a copy of the analytical air clearance results would be forwarded to EPA, these results have not yet been received. On December 9, 2010, the asbestos abatement subcontractor glove-bagged the ACM covering the two pipes on the second story of the southwest wing of Building 3. Asbestos lying on the third story floor of the southwest wing was also removed. The asbestos abatement subcontractor subsequently demobilized their equipment from the Site.
While conducting work in the basement in the collapsing roof area the asbestos abatement subcontractor exposed an approximately 100 square foot area of what appears to be soil contaminated with an unknown substance. The asbestos abatement prime contractor is making arrangements to have this contaminated soil sampled, as well as, the containers in the building.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
See Polrep 1.
2.1.4 Progress Metrics
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| Asbestos |
Solid |
40 cubic yards |
|
Landfill |
Grows Landfill North |
| |
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
2.2 Planning Section
|
|
|
|
2.2.1.1 Planned Response Activities
The PRP's contractors will conduct an asbestos abatement at the Site.
2.2.1.2 Next Steps
The PRP's contractor will sample/analyze the contaminated soil in this area, as well as, the contents of the containers in the building and subsequently conduct an asbestos abatement of the southern basement room.
2.2.2 Issues
|
|
|
2.3 Logistics Section
|
|
|
|
No information available at this time.
|
|
|
2.4 Finance Section
|
|
|
|
No information available at this time.
|
|
|
2.5 Other Command Staff
|
|
|
|
No information available at this time.
|
|
3. Participating Entities
|
|
|
No information available at this time.
|
|
4. Personnel On Site
|
|
|
No information available at this time.
|
|
5. Definition of Terms
|
|
|
No information available at this time.
|
|
6. Additional sources of information
|
|
|
No information available at this time.
|
|
7. Situational Reference Materials
|
|
|
No information available at this time.
|