U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portage Creek Area

All POL/SITREP's for this site Portage Creek Area
Kalamazoo, MI - EPA Region V
POLREP #9
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Portage Creek Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #9
Progress
Portage Creek Area
059B05
Kalamazoo, MI
Latitude: 42.2839750 Longitude: -85.5791570


To: Mark Mills, Michigan DNR
Daria Devantier, MDEQ
Debbie Jung, City of Kalamazoo
Lisa Williams, U.S. FWS
Todd Goeks, NOAA
Valincia Darby, Department of Interior

From: Craig Thomas, On-Scene Coordinator
Date: 5/12/2012
Reporting Period: 4/30/2012 - 5/12/2012

1. Introduction
  1.1 Background
   
Site Number: 059B05    Contract Number: EP-S5-08-02
D.O. Number: 0087    Action Memo Date: 7/5/2011
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: EPA    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 05
Mobilization Date: 9/26/2011    Start Date: 8/30/2011
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID: NA
ERNS No.: NA    State Notification: Yes
FPN#: NA    Reimbursable Account #: NA


1.1.1 Incident Category
Fund-lead removal action

1.1.2 Site Description
See POLREP #1

1.1.2.1 Location
See POLREP #1

1.1.2.2 Description of Threat
See POLREP #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
See POLREP #1

2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative
Crews continued mobilizing equipment and materials to the SA6 dredging area.  A large bypass pumping system was constructed, installed and tested to route the creekwater flow around the dredging area. The first section of 3 sheet pile coffer dams began to isolate dredging areas between Stockbridge Avenue and Lake Street.  Dredging operations are expected to begin in SA6 by the end of the month.

2.1.2 Response Actions to Date
From April 30 to May 12, U.S. EPA, START and ERRS contractors/sub-contractors conducted the following activities:

Site Activities - Staging Pad
- Shipped 3 loads of C&D debris (88.72 tons, ~130 yds) from staging pad to C&C Landfill in Marshall; and
- Received and staged coir logs for restoration activities along creek edge.

Site Activities - SA6
- Secured Lake Street entrance with temporary gate;
- Installed "Trucks Entering Highway" signs east and west of Stockbridge Avenue entrance;
- Created support and first aid area for work crews;
- Installed additional environmental controls in and around work area (silt fence, silt curtain, sand bags, geotextile in storm drains);
- Mobilized equipment (i.e. 2 24" pumps, wheel loader, fuel tanks), controls (i.e. sound dampening curtains, containment mat for fuel tanks) and materials (HDPE pipe) for bypass dewatering system;
- Excavated and stabilized sediment in creek bed to create sump for bypass dewatering pump intakes;
- Cleared and grubbed additional trees on east bank of creek to support 30" HDPE pipe;
- Fusion welded and installed over 950' of 30" HDPE pipe for bypass dewatering system;
- Installed gabion baskets to diffuse bypass system discharge at Lake Street bridge;
- Tested by pass pumping system (primary and backup pumps);
- Installed 6" sump pump at parking lot drain from Lake Street Barn parking lot;
- Installed first section of sheet piling near bypass pump at Stockbridge Avenue; and
- Conducted work area perimeter air monitoring.  Results continue to be below the action level of an average of 2.5 mg/m3 sustained for 1 minute.

Project Management Activities
- Conducted weekly update meetings with Kalamazoo City on site progress;
- Provided a site tour to natural resource representatives from MDEQ, U.S. FWS, and NOAA which included the completed SA7 excavation area and site preparations for dredging in SA6;
- Contracted with railway to maintain a flagger along railroad to ensure worker safety during bypass pumping system pipeline installation;
- Conducted door to door outreach to residents near the Stockbridge Avenue bridge regarding noise generation from creek bypass pumping system;
- Met with ecological consultant to identify Japanese Knotweed in SA6;
- Consulted MDARD for procedure to eradicate Japanese Knotweed identified in SA6;
- Conducted pre-excavation video survey along creek banks in SA5;
- Conduct data validation for post removal construction soil samples collected from SA7;
- Secured wet dredge and dewatering contract; and
- Finalized SA6 technical memorandum revision #2.

- 2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
The major PRP for this portion of the Allied Paper Inc./Portage Creek/Kalamazoo River Superfund site was dissolved through bankruptcy proceedings in April 2010.  Other PRPs are being evaluated.

2.1.4 Progress Metrics 
Waste Stream Medium Quantity Manifest # Treatment Disposal
C&D Debris solid waste 88.7 tons 1403353, 1403387,
14033497,
Disposal Subtitle D Landfill

  2.2 Planning Section
   

A summary of removal activities that will take place in the upcoming week(s) include:

Site Activities - Staging Pad
- Receive, dewater and load out contaminated sediments removed from SA6 for disposal; and
- Stage, maintain and support heavy equipment, materials and supplies for dredging operations.

Site Activities - SA6
- Complete installation of remaining sheet piling to isolate 3 dredging areas;
- Continue to construct working surface along creek banks to support dredging equipment;
- Construct sand bag coffer dam at Lake Street bridge;
- Start up bypass pumping system to divert creekwater around dredging area;
- Begin sediment excavation, solidification and transport of contaminated sediments from first isolation area; and
- Continue perimeter and personnel air monitoring near site activities.

Project Management Activities
- Continue weekly progress meetings with City of Kalamazoo;
- Complete site-specific restoration plans for SA5, SA6, and SA7 for review by trustees;
- Finalize plans to mobilize contractor for restoration activities after dredging operations are complete;
- Finalize plans for installation of creek de-watering system for second dredging area; and

- Complete needed repairs, mobilize and set up U.S. EPA's mobile water treatment system at John Street staging area for treatment of staging pad drainage water.

2.2.1 Anticipated Activities
See POLREP #2

2.2.1.1 Planned Response Activities
See above

2.2.1.2 Next Steps
See above

2.2.2 Issues
None


  2.3 Logistics Section
   

The current resources present on site during this reporting period include:

- Office trailers

- Portable restrooms and hand-washing stations
- Portable generators
- Submersible pumps
- Equipment storage container
- ERRS work crews and subcontractor work crews
- START sampling contractor
- Heavy equipment
- Water truck
- Street sweeper
- Truck wash
- Mixing boxes
- Frac (water) tanks
- Pressure wash trailer
- Bypass pumps and piping
- Sheet piling


  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    2.5.1 Safety Officer

Craig Thomas and Paul Ruesch, U.S. EPA FOSCs, are serving as safety officer(s).
The HASP is reviewed and signed by all site personnel.  All new personnel arriving on site are provided a site orientation and safety briefing. Safety meetings are held each morning with all workers to ensure safe daily operations.

2.6 Liaison Officer
Craig Thomas and Paul Ruesch, U.S. EPA FOSCs, are serving as liaison(s) with local officials and any other interested parties.

2.7 Information Officer
See Section 2.6

2.7.1 Public Information Officer
See Section 2.6

2.7.2 Community Involvement Coordinator
Don DeBlasio - U.S. EPA


3. Participating Entities
  3.1 Unified Command
N/A

3.2 Cooperating Agencies

U.S. Environmental Protection Agency

Michigan Department of Environmental Quality
Michigan Department of Agriculture and Rural Development

Michigan Department of Natural Resources

U.S. Fish and Wildlife Service

City of Kalamazoo:

            Department of Public Services

Parks and Recreation Department

Economic Development Department

Community Planning & Development

Public Safety Department

Fire Department

Police Department

            ReDevelopment Department
Bronson Methodist Hospital

Kalamazoo Nature Center


4. Personnel On Site
 

U.S. EPA - 2
ERRS contractor (Environmental Quality Management, Inc) - 6
CMC (subcontractor to EQM) - 6
Rain 4 Rent (subcontractor to EQM) - 4
START contractor (Weston/Dynamac) - 1


5. Definition of Terms
  C&D - Construction and Demolition (waste)
ERRS - Emergency and Rapid Response Services
FOSC - Federal On Scene Coordinator
U.S. FWS - United States Fish and Wildlife Service
HASP - Health and Safety Plan
HDPE - High density polyethylene (plastic)
mg/kg - milligrams per kilogram
mg/m3 - milligrams per cubic meter
MDARD - Michigan Department of Agriculture and Rural Development
MDEQ - Michigan Department of Environmental Quality
NA - Not Applicable
NOAA - National Oceanic and Atmospheric Administration
NPL - National Priorities List
PCB - polychlorinated biphenyl
ppm - parts per million
PRPs - Potentially Responsible Parties
RTK GPS - Real Time Kinematic Global Positioning System
SA - Slope Area
START - Superfund Technical Assessment and Response Team
U.S. EPA - United States Environmental Protection Agency



6. Additional sources of information
  6.1 Internet location of additional information/report

See the project website at http://www.epaosc.org/portagecreekarea.


6.2 Reporting Schedule
The next POLREP will be generated in approximately 2 weeks.

7. Situational Reference Materials
 

See the project website at http://www.epaosc.org/portagecreekarea

Additional information on the overall Kalamazoo River Project can be found at http://www.epa.gov/Region5/cleanup/kalproject/index.htm.



Click here to view Attached Images