U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portage Creek Area

All POL/SITREP's for this site Portage Creek Area
Kalamazoo, MI - EPA Region V
POLREP #12
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Portage Creek Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #12
Progress
Portage Creek Area
059B05
Kalamazoo, MI
Latitude: 42.2839750 Longitude: -85.5791570


To: Mark Mills, Michigan DNR
Daria Devantier, MDEQ
Debbie Jung, City of Kalamazoo
Lisa Williams, U.S. FWS
Todd Goeks, NOAA
Valincia Darby, Department of Interior

From: Craig Thomas, On-Scene Coordinator
Date: 6/22/2012
Reporting Period: 6/9/2012 - 6/22/2012

1. Introduction
  1.1 Background
   
Site Number: 059B05    Contract Number: EP-S5-08-02
D.O. Number: 0087    Action Memo Date: 7/5/2011
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: EPA    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 05
Mobilization Date: 9/26/2011    Start Date: 8/30/2011
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID: NA
ERNS No.: NA    State Notification: Yes
FPN#: NA    Reimbursable Account #: NA

1.1.1 Incident Category
Fund-lead removal action

1.1.2 Site Description
See POLREP #1

1.1.2.1 Location
See POLREP #1

1.1.2.2 Description of Threat
See POLREP #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
See POLREP #1

2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative
Dredging and backfilling operations were completed in SA6 (grids SA6-2 thru SA6-14).  Site controls, supplies and equipment is being demobilized from this area will be removed by the end of June.  Site preparation for dredging operations are underway along Axtell Creek, with dredging operations scheduled to begin in early July.

2.1.2 Response Actions to Date
From June 9 to June 22, EPA, START and ERRS contractors/sub-contractors conducted the following activities:

Site Activities - SA6
- Excavated and stabilized contaminated sediments from grids SA6-11 thru SA6-14;
- Completed post-excavation sampling in grids SA6-11 thru SA6-14 to confirm cleanup goals were met.  All confirmatory sample results for SA6 were under the performance standard of 10 mg/kg.  Two sample grid results were above the performance standard goal of 1 mg/kg.  Eight grids required over-excavation from the original target dredge depths.  One result for SA6-14 was pending from the laboratory at the time of this report and will be added to the table below once received;

GRID TOTAL EXCAVATION DEPTH (in) CONFIRMATION PCB RESULT (mg/kg)
SA6-2 30 0.62
SA6-3 30 0.775
SA6-4 30 < 0.130
SA6-5 36 0.875
SA6-6A 36 0.53
SA6-6B 42 0.654
SA6-7 36 0.654
SA6-8 30 3.75
SA6-9 36 1.54
SA6-10 42 0.888
SA6-11 42-54 0.54
SA6-12 42 0.72
SA6-13 30 0.256
SA6-14 36 at laboratory

- Completed backfilling in grids SA6-7 thru SA6-14;
- Removed all sheet pile coffer dams installed to isolate dredging areas;
- Removed groundwater de-watering systems;
- Began demobilization of site controls; and
- Conducted personnel air monitoring, stream turbidity, upstream/downstream water quality, noise level, and perimeter particulate monitoring in work areas with all results below action levels.
- Collected wipe samples from decontaminated equipment.

Site Activities - Staging Pad
- Received and further solidified contaminated sediments excavated from SA6;
- Loaded out 34 trucks of solidified sediments (PCB levels < 50ppm) for disposal at C&C Landfill in Marshall, MI;
- Loaded out 5 trucks of solidified sediments (PCB levels > 50ppm) for disposal at Wayne Disposal in Belleville, MI;
- Treated 33,530 gallons of contaminated drainage water in EPA's mobile wastewater treatment system, and collected effluent samples.

Site Activities - Axtell Creek
- Removed large trees along south bank and brush on north bank of creek;
- Prepared work area on south bank of creek for heavy equipment staging; and
- Began installation of sheet pile coffer dams to isolate dredging area.

Site Activities - SA5D
- Removed large diseased and/or dead trees along east and west banks of Portage Creek south of Crosstown Parkway.

Project Management Activities
- Conducted update meetings with Kalamazoo City on site progress;
- Met with sub-contractor regarding tree plantings for SA7, SA6 and SA5;
- Conducted site tour of staging pad area with State natural resource trustees and Bronson Methodist Hospital officials to discuss future use of property once project is complete; and
- Conducted data validation for post-removal confirmation sediment samples collected from SA6.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
The major PRP for this portion of the Allied Paper Inc./Portage Creek/Kalamazoo River Superfund site was dissolved through bankruptcy proceedings in April 2010.  Other PRPs are being evaluated.

2.1.4 Progress Metrics 
Waste Stream Medium Quantity Manifest # Treatment Disposal
Non-TSCA contaminated
sediments
solidified sediment 1739.34 tons NTSCA-045 to
NTSCA-078
disposal C&C Landfill,
Marshall, MI
TSCA contaminated
sediments
solidified sediment  221.46 tons
009133424JJK to
009133427JJK &
009133429JJK
disposal Wayne Disposal,
Belleville, MI

  2.2 Planning Section
   

A summary of removal activities that will take place in the upcoming week(s) include:

Site Activities - Staging Pad
- Treat contaminated water in EPA's mobile waste water treatment plant.

Site Activities - SA6
- Complete removal of site controls (i.e., bypass pumping system, frac tanks, wheel wash, etc.) from work area; and
- Complete streambank stabilization activities;

Site Activities - Axtell Creek
- Install sheet pile coffer dams to isolate dredging area;
- Install bypass pumping system around excavation area; and
- Install all other site controls and mobilize in heavy equipment/materials to support dredging activities.

Site Activities - SA5D
- Install sheet pile coffer dams at the Lake Street and Crosstown Parkway bridges.

Project Management Activities
- Continue weekly progress meetings with City of Kalamazoo;
- Solicit bids for installation/operation of Portage Creek bypass pumping system to isolate dredging areas in SA5D&C;
- Solicit bids for installation/operation of Portage Creek groundwater dewatering system in SA5D&C; and
- Complete site-specific restoration plans for SA5, SA6, and SA7 for review by trustees.

2.2.1 Anticipated Activities
See POLREP #2

2.2.1.1 Planned Response Activities
See above

2.2.1.2 Next Steps
See above

2.2.2 Issues
None


  2.3 Logistics Section
   

The current resources present on site during this reporting period include:

- Office trailers

- Portable restrooms and hand-washing stations
- Portable generators
- Submersible pumps
- Equipment storage container
- ERRS work crews and subcontractor work crews
- START sampling contractor
- Heavy equipment
- Water truck
- Street sweeper
- Truck wash
- Mixing boxes
- Frac (water) tanks
- Pressure wash trailer
- Bypass pumps and piping
- Groundwater de-watering pumps, wells and piping
- Sheet piling


  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    2.5.1 Safety Officer

Craig Thomas and Paul Ruesch serve as safety officer(s).  The HASP is reviewed and signed by all site personnel.  All new  personnel are provided a site orientation and safety briefing. Safety meetings are held each morning with all workers.

2.6 Liaison Officer
Craig Thomas and Paul Ruesch serve as liaison(s) with local officials and interested parties. 

2.7 Information Officer
See Section 2.6

2.7.1 Public Information Officer
See Section 2.6

2.7.2 Community Involvement Coordinator
Don DeBlasio - U.S. EPA


3. Participating Entities
  3.1 Unified Command
N/A

3.2 Cooperating Agencies

U.S. Environmental Protection Agency

Michigan Department of Environmental Quality
Michigan Department of Agriculture and Rural Development

Michigan Department of Natural Resources

U.S. Fish and Wildlife Service

City of Kalamazoo:

            Department of Public Services

Parks and Recreation Department

Economic Development Department

Community Planning & Development

Public Safety Department

Fire Department

Police Department

            ReDevelopment Department
Bronson Methodist Hospital

Kalamazoo Nature Center


4. Personnel On Site
 

U.S. EPA - 2
ERRS contractor (Environmental Quality Management, Inc) - 14
CMC (sheet pile sub-contractor to EQM) - 5
Terra Contracting (excavation sub-contractor to EQM) - 1
Total Tree Service (tree removal sub-contractor to EQM) - 6
START contractor (Dynamac) - 1
Fulton Trucking (trucking sub-contractor to EQM) - 2
Advance Security - 1

TOTAL PERSONNEL = 30


5. Definition of Terms
  C&D - Construction and Demolition (waste)
ERRS - Emergency and Rapid Response Services
FOSC - Federal On Scene Coordinator
U.S. FWS - United States Fish and Wildlife Service
HASP - Health and Safety Plan
HDPE - High density polyethylene (plastic)
mg/kg - milligrams per kilogram
mg/m3 - milligrams per cubic meter
MDARD - Michigan Department of Agriculture and Rural Development
MDEQ - Michigan Department of Environmental Quality
NA - Not Applicable
NOAA - National Oceanic and Atmospheric Administration
NPL - National Priorities List
NRDA - Natural Resource Damage Assessment
ntu - nephelometric turbidity units
PCB - polychlorinated biphenyl
ppm - parts per million
PRPs - Potentially Responsible Parties
RTK GPS - Real Time Kinematic Global Positioning System
SA - Slope Area
START - Superfund Technical Assessment and Response Team
U.S. EPA - United States Environmental Protection Agency



6. Additional sources of information
  6.1 Internet location of additional information/report

See the project website at http://www.epaosc.org/portagecreekarea.


6.2 Reporting Schedule
The next POLREP will be generated in approximately 2 weeks.

7. Situational Reference Materials
 

See the project website at http://www.epaosc.org/portagecreekarea

Additional information on the overall Kalamazoo River Project can be found at http://www.epa.gov/Region5/cleanup/kalproject/index.htm.



Click here to view Attached Images