U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portage Creek Area

All POL/SITREP's for this site Portage Creek Area
Kalamazoo, MI - EPA Region V
POLREP #17
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Portage Creek Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #17
Progress
Portage Creek Area
059B05
Kalamazoo, MI
Latitude: 42.2839750 Longitude: -85.5791570


To: Mark Mills, Michigan DNR
Daria Devantier, MDEQ
Debbie Jung, City of Kalamazoo
Lisa Williams, U.S. FWS
Todd Goeks, NOAA
Valincia Darby, Department of Interior

From: Craig Thomas, On-Scene Coordinator
Date: 8/31/2012
Reporting Period: 8/18/2012 - 8/31/2012

1. Introduction
  1.1 Background
   
Site Number: 059B05    Contract Number: EP-S5-08-02
D.O. Number: 0087    Action Memo Date: 7/5/2011
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: EPA    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 05
Mobilization Date: 9/26/2011    Start Date: 8/30/2011
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID: NA
ERNS No.:    State Notification: Yes
FPN#:    Reimbursable Account #:

1.1.1 Incident Category
Fund-lead removal action

1.1.2 Site Description
See POLREP #1

1.1.2.1 Location
See POLREP #1

1.1.2.2 Description of Threat
See POLREP #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
See POLREP #1

2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative
Dredging operations began in SA5D (Upjohn Park) on August 20. Contaminated sediment removal and backfilling was completed in grids SA5D-1 to SA5D-8 by August 31. Visible gross contamination and elevated PCB test results at target excavation depths (see Sections 2.1.2, 2.2 and 2.2.2) required additional excavation to meet the clean-up performance standard. Preparations are underway to begin dredging operations in SA5C immediately following completion of dredging/backfilling operations in SA5D.

2.1.2 Response Actions to Date
From August 18 to August 31, EPA, START and ERRS contractors conducted the following activities:

Site Activities - SA5D & SA5C
- Constructed sand-bag coffer dam to facilitate groundwater de-watering between the Upjohn Park footbridge and Crosstown Parkway;
- Removed the Upjohn Park footbridge to facilitate access for contaminated sediment excavation operations;
- Extended temporary fencing from the Upjohn Park footbridge to Crosstown Parkway;
- Fenced off sensitive drip line areas for trees in SA5C;
- Installed groundwater dewatering system from the Upjohn Park footbridge to Crosstown Parkway; and
- Excavated contaminated sediments from grids SA5D-1 to SA5D-8.

GRID TOTAL ESTIMATED EXCAVATION DEPTH (in) FINAL
CONFIRMATION PCB RESULT (mg/kg)
SA5D-1 54 ND
SA5D-2 60 0.098
SA5D-3 56 0.17
SA5D-4 59 0.21 
 SA5D-5  59  ND 
SA5D-6 56  ND 
 SA5D-7  50  ND 
SA5D-8 60 0.86 
                        ND: non-detect

Site Activities - Axtell Creek
- Removed isolation (groundwater) de-watering system, and
- Abandoned and sealed de-watering well boreholes with bentonite clay.

Site Activities - Staging Pad
- Solidified and loaded out 633.04 tons of TSCA (> 50ppm PCBs) contaminated sediments for disposal at Wayne Disposal landfill in Belleville, Michigan;
- Solidified and loaded out 2269.03 tons of non-TSCA (< 50ppm PCBs) contaminated sediments for disposal at C&C Landfill in Marshall, Michigan; and
- Treated 25,582 gallons of potentially contaminated contact water in EPA's mobile wastewater treatment plant, with a total of 471,083 gallons treated to date.

Project Management Activities
- Continued weekly progress meetings with City of Kalamazoo;
- Conducted data validation for post-removal confirmation sediment samples collected from SA5D;
- Met with Bronson Methodist Hospital officials regarding planning for access in SA5A; and
- Received post-excavation structural assessment for SA6.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
The major PRP for this portion of the Allied Paper Inc./Portage Creek/Kalamazoo River Superfund site was dissolved through bankruptcy proceedings in April 2010. Other PRPs are being evaluated.

2.1.4 Progress Metrics 
Waste Stream Medium Quantity Manifest # Treatment Disposal
TSCA contaminated
sediments
solidified sediment  633.04 tons 009077454JJK 
to
009077466JJK
disposal Wayne Disposal, Belleville, MI
Non-TSCA contaminated sediments solidified sediment  2269.03 tons NTSCA-101
to
NTSCA-144
 disposal C&C Landfill, Marshall MI
Scrap Tires solid  57 tires JC8-28-1  recycling Entech, Inc, White Pigeon, MI 
Corrugated cardboard boxes solid 100 lbs NA recycling municipal drop-off center
Dry cell batteries solid 25 lbs NA recycling federal drop-off center

  2.2 Planning Section
    A summary of removal activities that will take place from September 1 through September 14 include:
 
Site Activities - Staging Pad
- Continue de-watering and solidification of excavated sediments for transport;
- Continue transport of solidified sediments for disposal; and
- Continue treatment of contaminated water in EPA's mobile waste water treatment plant.

Site Activities - SA5D & SA5C
- Excavate, solidify and transport for disposal contaminated sediments from Portage Creek in grids SA5D-9 to SA5D-17 (between the Upjohn Park footbridge and Crosstown Parkway);
- Backfill grids SA5D-9 to SA5D-17 according to Restoration Plan;
- Install groundwater de-watering system from Crosstown Parkway to Vine Street;
- Install fencing on east and west banks between Crosstown Parkway & Vine Street; and
- Install wooden platform working surface on west bank of Portage Creek between Crosstown Parkway and Vine Street to support heavy equipment.

Project Management Activities
- Continue weekly progress meetings with City of Kalamazoo; and
- Complete pre-excavation assessments of SA5A and SA3A.

2.2.1 Anticipated Activities
See POLREP #2

2.2.1.1 Planned Response Activities
See above

2.2.1.2 Next Steps
See above

2.2.2 Issues
- Excavation of grids to initial target depths revealed visual paper pulp material. Therefore, many grids were over-excavated until that material was no longer visible.  Grid SA5D-7 was sampled at the initial target depth (36 inches), to verify that the suspected paper pulp material exceeded project performance standards. All confirmatory sample results from over-excavation in grids SA5D-1 to SA5D-8 were under the performance standard of 10 mg/kg as well as the performance standard goal of 1 mg/kg as listed below (see table).
  
GRID INITIAL TARGET DEPTH (in) INITIAL PCB RESULT(mg/kg) OVER
DIG
(in)
TOTAL ESTIMATED DEPTH (in) FINAL DEPTH PCB RESULT (mg/kg)
SA5D-1 30 -- 24 54 ND
SA5D-2 30 -- 30 60 0.098
SA5D-3 30 -- 26 56 0.17
SA5D-4 36 -- 23 59 0.21
SA5D-5 36 -- 23 59 ND
SA5D-6  36  --  20  56  ND 
SA5D-7 36  154 14 50 ND 
SA5D-8 36  -- 24  60  0.86 

- The additional over-excavation in grids SA5D-1 to SA5D-8 in Portage Creek resulted in increased costs
 and added expenses for personnel, equipment, transportation, disposal, sampling and backfill material. 

  2.3 Logistics Section
   

The current resources present on site during this reporting period include:

- Office trailers

- Portable restrooms and hand-washing stations
- Portable generators
- Submersible pumps
- Equipment storage container
- ERRS work crews and subcontractor work crews
- START sampling contractor
- Heavy equipment
- Water truck
- Street sweeper
- Mixing boxes
- Frac (water) tank
- Pressure wash trailer
- Bypass pumps and piping
- Sheet piling and steel bridge personnel support structures
- Mobile wastewater treatment plant
- Temporary steel bridge

- Monitoring Equipment


  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    2.5.1 Safety Officer

Craig Thomas and Paul Ruesch serve as safety officer(s).  The HASP is reviewed and signed by all site personnel.  All new personnel, including sub-contractors, are provided a site orientation and safety briefing. Safety meetings are held each morning with all site workers.

A safety audit was conducted on August 30 by Federal Occupational Health.  A few minor issues were identified which will be corrected in the next reporting period.

2.6 Liaison Officer
Craig Thomas and Paul Ruesch serve as liaison(s) with local officials and interested parties. 

2.7 Information Officer
See Section 2.6

2.7.1 Public Information Officer
See Section 2.6

2.7.2 Community Involvement Coordinator
Don DeBlasio - U.S. EPA


3. Participating Entities
  3.1 Unified Command
N/A

3.2 Cooperating Agencies

U.S. Environmental Protection Agency

Michigan Department of Environmental Quality
Michigan Department of Agriculture and Rural Development

Michigan Department of Natural Resources

U.S. Fish and Wildlife Service

City of Kalamazoo:

            Department of Public Services

Parks and Recreation Department

Economic Development Department

Community Planning & Development

Public Safety Department

Fire Department

Police Department

            ReDevelopment Department
Bronson Methodist Hospital

Kalamazoo Nature Center


4. Personnel On Site
 

U.S. EPA - 2
ERRS contractor (Environmental Quality Management, Inc) - 13
START contractor (Dynamac/Weston) - 1
CMC Contractors (excavation subcontractor) - 1
Rain for Rent (groundwater extraction subcontractor) - 2
Farm & Garden (fencing subcontractor) - 2

TOTAL PERSONNEL = 19


5. Definition of Terms
  C&D - Construction and Demolition (waste)
ERRS - Emergency and Rapid Response Services
FOSC - Federal On Scene Coordinator
U.S. FWS - United States Fish and Wildlife Service
HASP - Health and Safety Plan
HDPE - High density polyethylene (plastic)
mg/kg - milligrams per kilogram
mg/m3 - milligrams per cubic meter
MDARD - Michigan Department of Agriculture and Rural Development
MDEQ - Michigan Department of Environmental Quality
NA - Not Applicable
NOAA - National Oceanic and Atmospheric Administration
NPL - National Priorities List
NRDA - Natural Resource Damage Assessment
ntu - nephelometric turbidity units
PCB - polychlorinated biphenyl
ppm - parts per million
PRPs - Potentially Responsible Parties
RTK GPS - Real Time Kinematic Global Positioning System
SA - Slope Area
START - Superfund Technical Assessment and Response Team
U.S. EPA - United States Environmental Protection Agency



6. Additional sources of information
  6.1 Internet location of additional information/report

See the project website at http://www.epaosc.org/portagecreekarea.


6.2 Reporting Schedule
The next POLREP will be generated in approximately 2 weeks.

7. Situational Reference Materials
 

See the project website at http://www.epaosc.org/portagecreekarea

Additional information on the overall Kalamazoo River Project can be found at http://www.epa.gov/Region5/cleanup/kalproject/index.htm.



Click here to view Attached Images