U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portage Creek Area

All POL/SITREP's for this site Portage Creek Area
Kalamazoo, MI - EPA Region V
POLREP #21
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Portage Creek Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #21
Progress
Portage Creek Area
059B05
Kalamazoo, MI
Latitude: 42.2839750 Longitude: -85.5791570


To: Mark Mills, Michigan DNR
Daria Devantier, MDEQ
Debbie Jung, City of Kalamazoo
Lisa Williams, U.S. FWS
Todd Goeks, NOAA
Valincia Darby, Department of Interior

From: Craig Thomas, On-Scene Coordinator
Date: 10/31/2012
Reporting Period: 10/13/2012 - 10/31/2012

1. Introduction
  1.1 Background
   
Site Number: 059B05    Contract Number: EP-S5-08-02
D.O. Number: 0087    Action Memo Date: 7/5/2011
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: EPA    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 05
Mobilization Date: 9/26/2011    Start Date: 8/30/2011
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID: NA
ERNS No.:    State Notification: Yes
FPN#:    Reimbursable Account #:

1.1.1 Incident Category
Fund-lead removal action

1.1.2 Site Description
See POLREP #1

1.1.2.1 Location
See POLREP #1

1.1.2.2 Description of Threat
See POLREP #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
See POLREP #1

2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative
Seasonal demobilization operations were conducted during this reporting period.  In addition, site preparations began in both SA5A and SA3A in anticipation of removal activities next construction season.

2.1.2 Response Actions to Date
From October 15 to October 31, EPA, START and ERRS contractors conducted the following activities:

Site Activities - Axtell Creek, SA5D & SA5C
- Demobilized pumps, de-watering system, engineering & environmental controls and equipment from SA5C;
- Removed curb cuts and replaced damaged sections of sidewalks;
- Conducted post-construction site structural feature assessment; and
- Began site restoration activities in accordance with the site Restoration Plan.

Site Activities - SA5A
- Conducted pre-construction sampling and pre-removal contaminated sediment confirmation sampling in each grid;
- Staged bypass pump discharge pipes on east bank for the winter to save time and re-mobilization costs; and
- Removed trees, brush and fencing from creek banks in preparation for removal operations next year.

Site Activities - SA3A
- Conducted pre-removal contaminated sediment confirmation sampling;
- Constructed an aggregate access road and staging area for equipment and load-out pad; and
- Removed trees and brush from creek banks in preparation for removal operations next year.

Site Activities - Staging Pad
- Solidified and loaded out 1205.32 tons of non-TSCA (< 50ppm PCBs) contaminated sediments for disposal at C&C Landfill in Marshall, Michigan;
- Treated 42,344 gallons of potentially contaminated contact water in EPA's mobile wastewater treatment plant, with a total of 695,715 gallons treated to date;
- Shut down EPA's mobile waste water treatment plant for the season and demobilized support trailer; and
- Pumped out and transport 10,000 gallons of potentially contaminated contact water from the staging pad sump for treatment off site.

Project Management Activities
- Continued weekly progress meetings with City of Kalamazoo;
- Conducted data validation for additional post-removal confirmation sediment samples collected from SA5C&D;
- Continued discussions with property owners in SA5A, SA3A, SA1C and SA1B regarding site access, preparation and restoration; and
- Completed implementation of seasonal site shut-down / demobilization plan;

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
See POLREP #1

2.1.4 Progress Metrics
 
Waste Stream Medium Quantity Manifest # Treatment Disposal
Non-TSCA contaminated sediments solidified sediment  1205.32 tons NTSCA-190
to
NTSCA-213
disposal C&C Landfill, Marshall MI
Construction & Demolition solid waste 13.94 tons 23922 disposal C&C Landfill, Marshall, MI
Scrap Steel  scrap metal 460 lbs  n/a recycling Shupan Recycling
Shipping Pallets wood 100 n/a recycling Holland Pallet
 Tires tires 38  n/a   recycling Tire Reclaimers 

  2.2 Planning Section
    A summary of removal activities that will take place from October 31 through the end of the year include:
 
Site Activities - Staging Pad
- Continue to pump out and transport potentially contaminated contact water from the staging pad sump for treatment off site on an as-needed basis.

Site Activities - Axtell Creek, SA5D & SA5C
- Complete restoration activies according to site Restoration Plan.

Project Management Activities
- Conduct data validation for pre-removal confirmation core sampling conducted in SA5A & SA3A as well as post-construction sampling in SA5D;
- Review Post-Removal Structure Feature Assessment rep[ort for Axtell Creek, SA5D & SA5C;
- Obtain access agreements for properties in SA5A, SA3A, SA1C and SA1B; and
- Plan for removal opeations in SA5A, SA3A, SA1C and SA1B during the next construction season.

2.2.1 Anticipated Activities
See POLREP #2

2.2.1.1 Planned Response Activities
See above

2.2.1.2 Next Steps
See above

2.2.2 Issues
None

  2.3 Logistics Section
   

The current resources present on site during this reporting period include:

- Office trailers

- Portable restrooms and hand-washing stations (demobilized)
- Portable generators (demobilized)
- Submersible pumps (demobilized)
- Equipment storage container
- ERRS work crews and subcontractor work crews
- START sampling contractor (demobilized)
- Heavy equipment (demobilized)
- Water truck (demobilized)
- Street sweeper (demobilized)
- Mixing boxes
- Frac (water) tank (demobilized)
- Pressure wash trailer (demobilized)
- Bypass pumps and piping (demobilized)
- Sheet piling and steel bridge personnel support structures (demobilized)
- Mobile wastewater treatment plant
- Temporary steel bridge (demobilized)

- Monitoring Equipment (demobilized)

The only equipment that will remain on site during the seasonal de-mobilization will be the office trailers, equipment storage container and EPA's mobile wastewater treatment plant.


  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    2.5.1 Safety Officer

Craig Thomas and Paul Ruesch serve as safety officer(s).  The HASP is reviewed and signed by all site personnel.  All new personnel, including sub-contractors, are provided a site orientation and safety briefing. Safety meetings are held each morning with all site workers.

2.6 Liaison Officer
Craig Thomas and Paul Ruesch serve as liaison(s) with local officials and interested parties. 

2.7 Information Officer
See Section 2.6

2.7.1 Public Information Officer
See Section 2.6

2.7.2 Community Involvement Coordinator
Don DeBlasio - U.S. EPA


3. Participating Entities
  3.1 Unified Command
N/A

3.2 Cooperating Agencies

U.S. Environmental Protection Agency

Michigan Department of Environmental Quality
Michigan Department of Agriculture and Rural Development

Michigan Department of Natural Resources

U.S. Fish and Wildlife Service

City of Kalamazoo:

            Department of Public Services

Parks and Recreation Department

Economic Development Department

Community Planning & Development

Public Safety Department

Fire Department

Police Department

            ReDevelopment Department
Bronson Methodist Hospital

Kalamazoo Nature Center


4. Personnel On Site
 

U.S. EPA - 2
ERRS contractor (Environmental Quality Management, Inc) - 13
START contractor (Dynamac/Weston) - 1
CMC Contracting (sheet pile removal subcontractor) - 5
Rain for Rent (groundwater extraction subcontractor) - 2
Katerberg Verhage (restoration subcontractor)  - 3
Farm & Garden/Viskers (fencing contractor) - 2
Total Tree Service - 7
Baker Corporation Pump Division - 3

TOTAL PERSONNEL = 38


5. Definition of Terms
  C&D - Construction and Demolition (waste)
ERRS - Emergency and Rapid Response Services
FOSC - Federal On Scene Coordinator
U.S. FWS - United States Fish and Wildlife Service
HASP - Health and Safety Plan
HDPE - High density polyethylene (plastic)
mg/kg - milligrams per kilogram
mg/m3 - milligrams per cubic meter
MDARD - Michigan Department of Agriculture and Rural Development
MDEQ - Michigan Department of Environmental Quality
NA - Not Applicable
NOAA - National Oceanic and Atmospheric Administration
NPL - National Priorities List
NRDA - Natural Resource Damage Assessment
ntu - nephelometric turbidity units
PCB - polychlorinated biphenyl
ppm - parts per million
PRPs - Potentially Responsible Parties
RTK GPS - Real Time Kinematic Global Positioning System
SA - Slope Area
START - Superfund Technical Assessment and Response Team
U.S. EPA - United States Environmental Protection Agency



6. Additional sources of information
  6.1 Internet location of additional information/report

See the project website at http://www.epaosc.org/portagecreekarea.


6.2 Reporting Schedule
The next POLREP will be generated as needed.

7. Situational Reference Materials
 

See the project website at http://www.epaosc.org/portagecreekarea

Additional information on the overall Kalamazoo River Project can be found at http://www.epa.gov/Region5/cleanup/kalproject/index.htm.



Click here to view Attached Images