Portage Creek Area

All POL/SITREP's for this site Portage Creek Area
Kalamazoo, MI - EPA Region V
POLREP #38
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Portage Creek Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #38
Progress
Portage Creek Area
059B05
Kalamazoo, MI
Latitude: 42.2839750 Longitude: -85.5791570


To: Mark Mills, Michigan DNR
Daria Devantier, MDEQ
Debbie Jung, City of Kalamazoo
Lisa Williams, U.S. FWS
Todd Goeks, NOAA
Valincia Darby, Department of Interior

From: Craig Thomas, On-Scene Coordinator
Date: 10/25/2013
Reporting Period: 10/12/2013 - 10/25/2013

1. Introduction
  1.1 Background
   
Site Number: 059B05    Contract Number: EP-S5-08-02
D.O. Number: 0087    Action Memo Date: 7/5/2011
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: EPA    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 05
Mobilization Date: 9/26/2011    Start Date: 8/30/2011
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID: NA
ERNS No.:    State Notification: Yes
FPN#:    Reimbursable Account #:

1.1.1 Incident Category
Fund-lead removal action

1.1.2 Site Description
See POLREP #1

1.1.2.1 Location
See POLREP #1

1.1.2.2 Description of Threat
See POLREP #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
See POLREP #1

2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative
All equipment, supplies and materials were removed from SA1A & SA1B support areas. Final restoration of work areas is underway. The John Street staging pad is being removed and final preparations are underway to demobilize trailers, EPA's mobile wastewater treatment plant, storage containers and offices from the site.

2.1.2 Response Actions to Date
From October 12 to October 25, EPA and ERRS contractors conducted the following activities:

Site Activities - John Street Staging Area
- Treated 625 gallons of potentially contaminated contact water in EPA's mobile wastewater treatment plant, for a total of 1,125,924 gallons treated during the entire project;  
- Removed filtration media and cleaned out EPA's mobilize wastewater treatment plant in preparation for demobilization;
- Removed 10,800 gallons of potentially contaminated contact water from the staging pad sump via tanker truck;
- Began dismantlement of staging pad for removal;
- Loaded out timber mats for disposal at approved landfill facility; and
- Decontaminated, wipe sampled and demobilized heavy equipment no longer needed for the project.

Site Activities - SA1A
- Completed removal of staging and support area equipment, materials and supplies;
- Re-constructed sections of KRVT boardwalk removed to make room for bypass pumping system;
- Replaced light post removed for construction activities;
- Re-opened KRVT (recreational trail) between King Highway and Harrison Street for pedestrian use; and
- Completed bank stabilization, restoration and temporary seeding.

Site Activities - SA1B
- Completed removal of staging and support area equipment, materials and supplies; and
- Re-constructed, stabilized, and temporarily restored area with grass seed & straw.

Project Management Activities
- Continued weekly progress meetings with City of Kalamazoo, including property owners upon request;
- Conducted landscaping maintenance & irrigation in Rose Park;
- Solicited bids for repair of concrete & asphalt surfaces impacted during construction activities in SA5A, SA3A, SA1B & SA1A;
- Solicited bid for final restoration work according to area-specific restoration plans in SA1A & SA5A; and
- Continued development of project final report.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
See POLREP #1

2.1.4 Progress Metrics
 
Waste Stream Medium Quantity Manifest # Treatment Disposal
Potentially contaminated run-off water from staging pad wastewater  10,800 gal 005471267FLE -005471268FLE  treatment  Industrial Waste Service, Inc., Holland, MI 
Timber Mats wood timbers 169.19 tons  NNTSCA-001
to
NNTSCA-009
disposal  Ottawa County Farms Landfill, Coopersville, MI
Scrap metal steel 11,520 lbs 903203 recycling Shupan Metals

 

  2.2 Planning Section
    Removal activities anticipated to take place from October 26 to November 8 include the following:
 
Site Activities - John Street Staging Area
- Remove remaining contact water from the staging pad sump with tanker trucks (if necessary);
- Remove staging pad for transport and disposal at approved landfill facility;
- Demobilize EPA's mobile wastewater treatment plant and support trailer/equipment;
- Decontaminate, wipe sample and demobilize remaining heavy equipment; and
- Demobilize storage container, trailers and offices.

Site Activities - SA1A & B
- Restore vegetation according to area-specific restoration plan; and
- Replace and repair impacted sidewalk, curb and paved parking lots.

Site Activities - SA5A
- Conduct final restoration activities on east bank according to area-specific restoration plan; and
- Replace and repair impacted sidewalk sections.

Site Activities - SA3A
- Replace and repair impacted sidewalk, street curbs and entrance aprons.

Project Management Activities
- Continue progress meetings with City of Kalamazoo, and property owners, as appropriate;
- Continue development of project final report; and
- Commence project close-out activities.

2.2.1 Anticipated Activities
See POLREP #2

2.2.1.1 Planned Response Activities
See above

2.2.1.2 Next Steps
See above

2.2.2 Issues
None

  2.3 Logistics Section
   

The current resources present on site during this reporting period include:

- Office trailers
- Portable restrooms & hand-washing stations
- Equipment storage container
- ERRS work crews and subcontractor work crews
- START sampling contractor
- Heavy equipment
- Water truck
- Frac (water) tank
- Pressure wash trailer
- Mobile wastewater treatment plant


  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    2.5.1 Safety Officer

Craig Thomas, Paul Ruesch and Andy Maguire serve as safety officer(s). The HASP is reviewed and signed by all site personnel. All new personnel, including sub-contractors, are provided a site orientation and safety briefing. Safety meetings are held each morning with all site workers.

2.6 Liaison Officer
Craig Thomas, Paul Ruesch and Andy Maguire serve as liaison(s) with local officials and interested parties.

2.7 Information Officer
See Section 2.6 
 
2.7.1 Public Information Officer
See Section 2.6

2.7.2 Community Involvement Coordinator
Don DeBlasio - U.S. EPA


3. Participating Entities
  3.1 Unified Command
N/A

3.2 Cooperating Agencies

U.S. Environmental Protection Agency

Michigan Department of Environmental Quality
Michigan Department of Agriculture and Rural Development

Michigan Department of Natural Resources

U.S. Fish and Wildlife Service

City of Kalamazoo:

            Department of Public Services
            Parks and Recreation Department
            Economic Development Department
            Community Planning & Development
            Public Safety Department
            Fire Department
            Police Department
            Redevelopment Department
Bronson Methodist Hospital

Kalamazoo Nature Center


4. Personnel On Site
 

U.S. EPA - 2
START contractor (Weston Solutions) - 1
ERRS contractor (Environmental Quality Management, Inc) - 8
Fulton Trucking - 2

TOTAL PERSONNEL = 13


5. Definition of Terms
  ERRS - Emergency and Rapid Response Services
FOSC - Federal On Scene Coordinator
HASP - Health and Safety Plan
KRVT - Kalamazoo River Valley Trail
mg/kg - milligrams per kilogram
mg/m3 - milligrams per cubic meter
MDEQ - Michigan Department of Environmental Quality
NA - Not Applicable
NPL - National Priorities List
PCB - polychlorinated biphenyl
ppm - parts per million
SA - Slope Area
START - Superfund Technical Assessment and Response Team
U.S. EPA - United States Environmental Protection Agency

6. Additional sources of information
  6.1 Internet location of additional information/report

See the project website at http://www.epaosc.org/portagecreekarea.


6.2 Reporting Schedule
The next POLREP will be generated on November 8.

7. Situational Reference Materials
 

See the project website at http://www.epaosc.org/portagecreekarea

Additional information on the overall Kalamazoo River Project can be found at http://www.epa.gov/Region5/cleanup/kalproject/index.htm.