Orofino Asbestos Site

<<  <  1 2 3  >  >> 
Reconstruction of asbestos-soils repository retaining wall.<br />Date Taken: 9/18/2012<br />Category: 2012<br />Latitude: <br />Longitude: <br />Tags:
Deconstruction of repository retaining wall.
<br />Date Taken: 8/28/2012<br />Category: 2012<br />Latitude: <br />Longitude: <br />Tags:
Asphalt cutting in the asphalt repair area.<br />Date Taken: 4/21/2015<br />Category: 2015<br />Latitude: <br />Longitude: <br />Tags:
Removing asphalt in the asphalt repair area.<br />Date Taken: 4/21/2015<br />Category: 2015<br />Latitude: 46.4947966666667<br />Longitude: -116.30495<br />Tags:
Removing asphalt from the asphalt repair area. <br />Date Taken: 4/21/2015<br />Category: 2015<br />Latitude: 46.4945833333333<br />Longitude: -116.304331666667<br />Tags:
Removing asphalt from the asphalt repair area.<br />Date Taken: 4/21/2015<br />Category: 2015<br />Latitude: 46.4945116666667<br />Longitude: -116.304735<br />Tags:
Preparing liner in the bed of truck for waste material.<br />Date Taken: 4/21/2015<br />Category: 2015<br />Latitude: 46.494575<br />Longitude: -116.304315<br />Tags:
Loading waste material into lined truck.<br />Date Taken: 4/21/2015<br />Category: 2015<br />Latitude: 46.4947383333333<br />Longitude: -116.304486666667<br />Tags:
Excavating asbestos-contaminated soil under asphalt.<br />Date Taken: 4/22/2015<br />Category: 2015<br />Latitude: 46.4949833333333<br />Longitude: -116.304496666667<br />Tags:
Backfilling western section of asphalt repair area with 3/4-inch minus gravel.<br />Date Taken: 4/23/2015<br />Category: 2015<br />Latitude: 46.4946216666667<br />Longitude: -116.304363333333<br />Tags:
Compacting backfill material. <br />Date Taken: 4/23/2015<br />Category: 2015<br />Latitude: 46.4948266666667<br />Longitude: -116.304956666667<br />Tags:
Beginning to spread topsoil at the dry retention basin<br />Date Taken: 4/21/2015<br />Category: 2015<br />Latitude: 46.4940233333333<br />Longitude: -116.30546<br />Tags:
Spreading topsoil at the dry retention basin.<br />Date Taken: 4/21/2015<br />Category: 2015<br />Latitude: 46.4947516666667<br />Longitude: -116.304983333333<br />Tags:
Spreading topsoil at the dry retention basin.<br />Date Taken: 4/21/2015<br />Category: 2015<br />Latitude: <br />Longitude: <br />Tags:
Spreading topsoil at dry retention basin.<br />Date Taken: 4/22/2015<br />Category: 2015<br />Latitude: 46.4945633333333<br />Longitude: -116.305103333333<br />Tags:
Existing corrugated metal pipe surrounding drywell, and exposed PVC liner.<br />Date Taken: 4/22/2015<br />Category: 2015<br />Latitude: 46.49459<br />Longitude: -116.305166666667<br />Tags:
Cutting corrugated metal pipe (CMP) to level of PVC liner.<br />Date Taken: 4/22/2015<br />Category: 2015<br />Latitude: 46.4946266666667<br />Longitude: -116.305066666667<br />Tags:
Removing gravel inside CMP to allow room for PVC liner. <br />Date Taken: 4/22/2015<br />Category: 2015<br />Latitude: 46.4946866666667<br />Longitude: -116.305133333333<br />Tags:
Dry well after CMP is cut to level of PVC liner and PVC liner is placed inside the CMP.<br />Date Taken: 4/22/2015<br />Category: 2015<br />Latitude: 46.4946416666667<br />Longitude: -116.305301666667<br />Tags:
Installing washed drain rock around dry well.<br />Date Taken: 4/23/2015<br />Category: 2015<br />Latitude: 46.4947183333333<br />Longitude: -116.305015<br />Tags: