1. Introduction
|
|
|
1.1 Background
|
|
|
|
|
Site Number: |
A4QL |
|
Contract Number: |
EP-S4-07-04 |
|
D.O. Number: |
105 |
|
Action Memo Date: |
9/14/2010 |
|
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
|
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
|
NPL Status: |
Non NPL |
|
Operable Unit: |
|
|
Mobilization Date: |
9/29/2010 |
|
Start Date: |
9/29/2010 |
|
Demob Date: |
|
|
Completion Date: |
|
|
CERCLIS ID: |
NCD986232213 |
|
RCRIS ID: |
|
|
ERNS No.: |
|
|
State Notification: |
03/12/2010 |
|
FPN#: |
|
|
Reimbursable Account #: |
|
For Site Actions that occurred prior to this reporting period and background information, please refer to previous Pollution Reports.
|
|
2. Current Activities
|
|
|
2.1 Operations Section
|
|
|
|
The following actions took place during this reporting period:
- ERRS continued to demolish the ASTs and tanker trailers onsite. During this reporting period, 12 ASTs, 3 tanker trailers, and one box trailer were demolished for a total of 19 tons of steel and 1.9 tons of aluminum scrapped.
- ERRS also continued to mix the remianing sludges onsite with the cotton tash. 65,845 gallons of sludges were solidified accounting for 21 loads of material shipped off-site..
- START continued to monitor the air in the vicinity of the tanks and prepare samples for disposal of the solidified materials.
- No work took place on site on 1/10/11 due to heavy snow and ice. Work resumed on 1/11/11.
|
|
|
2.2 Planning Section
|
|
|
|
2.2.1 Anticipated Activities
2.2.1.1 Planned Response Activities
During the next reporting period ERRS the following activities are planned:
- ERRS will solidify and dispose of any remaining sludges onsite;
- Recyclable materials (tires, steel, aluminum, etc.) will continue to be removed from site;
- START will conduct soil sampling in probable impacted areas to determine the need for any soil removal;
- If needed, ERRS will conduct soil removal;
- ERRS will conduct site restoration activities such as removing impacted concrete, pressure washing impacted surfaces, and grading.
2.2.1.2 Next Steps
Beyond the tasks listed above, the installation of a Site monitoring well may be completed if deemed appropriate.
2.2.2 Issues
|
|
|
2.3 Logistics Section
|
|
|
|
At this time, this Site poses no logistical issues.
|
|
|
2.4 Finance Section
|
|
|
|
2.4.1 Narrative
The below accounting of expenditures are an estimate based on figures known to the OSC at the time this report was written. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
|
|
|
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$950,000.00 |
$586,000.00 |
$364,000.00 |
38.32% |
| IAGs |
$25,000.00 |
$0.00 |
$25,000.00 |
100.00% |
| START |
$175,000.00 |
$106,000.00 |
$69,000.00 |
39.43% |
|
Intramural Costs
|
| USEPA - Direct (Region, HQ) |
$10,000.00 |
$8,000.00 |
$2,000.00 |
20.00% |
| |
| Total Site Costs |
$1,160,000.00 |
$700,000.00 |
$460,000.00 |
39.66% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
|
|
|
2.5 Other Command Staff
|
|
|
|
No information available at this time.
|
|
3. Participating Entities
|
|
|
No information available at this time.
|
|
4. Personnel On Site
|
|
|
Maximum staffing during this reporting period:
1 - EPA OSC
1 - START (Otie)
6 - ERRS (ER)
|
|
5. Definition of Terms
|
|
|
AST - Above Ground Storage Tank
BTU - British Thermal Unit
CI - Civil Investigator
EPA - Environmental Protection Agency
EPM - Enforcement Project Manager
ERRB - Emergency Response and Removal Branch
ERRS - Emergency and Rapid Response Services
NFPA - National Fire Protection Association
NPP - National Petroleum Packers
OSC - On Scene Coordinator
PPE - Personal Protective Equipment
PRP - Potentially Responsible Party
RFQ - Request For Quote
START - Superfund Technical Assessment and Response Team
|
|
6. Additional sources of information
|
|
|
No information available at this time.
|
|
7. Situational Reference Materials
|
|
|
No information available at this time.
|
|
POLREP #10 Last Updated 2/2/2011
|